A new Substation and Switchroom building comprising a relevant

Donegal, Donegal · Donegal

Source notice reference
SN0013899DL
Commencement date
2026-03-20
Planning reference
20/51194
Planning authority
Donegal County Council
Project type
New build
Floor area
30 m² · per notice; not summed
Indexed source check
2026-06-09T15:11:14Z

Public-safe works description

The construction of a new Substation and Switchroom building comprising a relevant floor area of approx. 41.8 sqm. The Substation and Switchroom building is separated into two separate compartments. One compartment houses the ESB Substation, and the other compartment houses the Switch room.