← Complete commencement inventory

BCMS open-data feed

Upgrade works to be carried out at the Nephin Group Water Scheme

Cloughbrack Far, Mayo · Mayo

Source notice reference
CN0137492MO
Commencement date
2026-01-23
Planning reference
P24/528
Planning authority
Mayo County Council
Project type
Change of use
Floor area
200 m² · per notice; not summed
Indexed source check
2026-06-09T15:11:14Z

Public-safe works description

Upgrade works to be carried out at the Nephin Group Water Scheme site at Cloghbrack including repurposing construction/ installation of tanks of tanks, relocation of equipment and tanks, installation of a UV reactor, addition of a THM stripper and upgrade of Motor Control Centre, modifications to pumps pipework and intakes and associated engineering works. Works will also include modifications to onsite storage areas and installation of a new Programmable Logic Controllers (PLC) and Human Machine Interface (HMI) screens. All works will be conducted within the existing GWS Site.

This is one source-family notice identity, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.

Open grouped project and every phase · Open official source