Commencement notice group

Housing commencement notices — Loughlinstown

Dublin, Dublin

4 separate notices · latest notified commencement 06 May 2019 · planning reference supplied

Source notices
4
Latest notified commencement
06 May 2019
Latest notice
16,665 m²
Planning references supplied
P/1244/18
Public location
Dublin, Dublin

Public source geography

Site location

Public site / locality
Dublin, Dublin
County
Dublin

Public site labels seen across the notices

  • Loughlinstown, Dublin
  • County Dublin, Dublin
  • Cherrywood, Co
  • Cherrywood Town Centre 4 at Cherrywood, Dublin 18

Notice coordinates differ materially, so no combined point is shown. Use the per-notice location actions in the timeline.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Project documents

Drawings & planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

Planning referenceP/1244/18

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

SN0004170DR BCMS open-data feed

This application is for alterations to the construction of the shared basement / podium structure at Cherrywood TC2 development (approved FSC Reg Ref 18/8075), to include basement area previously omitted on commencement notice ref: 8417855, submitted, at TC2, Cherrywood, Dublin 18

16,665 m² · stated on this notice

Planning reference P/1244/18
CN0048175DR BCMS open-data feed

Construction of 2-level shared basement / podium structure including 9 no.apartment units (level -1) as part of the phased construction to completion of TC2 Developments: Construction of new building: Two mixed use blocks situated over a shared basement; and all associated site development works including a shared hotel ramp, retail ramp access, shared attenuation tank and structure to Grand Parade at Cherrywood, Co. Dublin

9 units · 37,588 m² · stated on this notice

Planning reference P/1244/18
CN0045592DR BCMS owner-supplied export

Soil removal and site clearance at Cherrywood Town Centre 4 at Cherrywood, Dublin 18.

173 units · 48,552 m² · stated on this notice

Planning reference P/1244/18 Developer stated: Matsack Trust Ltd
CN0045568DR BCMS owner-supplied export

Soil removal and site clearance at Cherrywood Town Centre 4 at Cherrywood, Dublin 18

1 unit · 48,552 m² · stated on this notice

Planning reference P/1244/18

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.