Commencement notice group
Unit E1 Horizon Logistics Park — commencement notices
Co. Dublin, Dublin
5 unique commencement events · latest notified commencement 03 Aug 2026 · planning reference supplied
- Unique commencement events
- 5
- Latest notified commencement
- 03 Aug 2026
- Latest notice
- 12,578 m²
- Planning references supplied
- FW22A/0079
- Public location
- Co. Dublin, Dublin
Commencement and completion records
Planning, start and completion evidence
The certificate is linked to its commencement notice. A corresponding planning record has not yet been established from the available source evidence.
- Exact planning records
- Official record actions
- 0
- Explicit planning relationships
- Duplicate source rows consolidated
- Exact completion events
Planning-anchored public geography
Site identity and location
- Canonical public locality
- Co. Dublin, Dublin
- County
- Dublin
Notice location variants
- Dublin, Dublin CN0145898FL, CN0104036FL, CN0104035FL, CN0101648FL
- Unit E1 Horizon Logistics Park, off R108, at the townlands of Merryfalls & Silloge, St CN0145898FL
- Unit E Horizon Logistics Park, Harristown, St Margaret’s, Swords, Co CN0104036FL
- Unit C Horizon Logistics Park, Harristown, St Margaret’s, Swords, Co CN0104035FL
- horizon business park (known as Unit C) CN0102519FL
- Horizon Logistics Park (Known as Site E2), Harristown, St CN0101648FL
- Notice source points are up to 647 m apart, so no combined representative point is shown.
Source positions remain separate:
- CN0145898FL · 53.417360, -6.274222 Open point
- CN0104036FL · 53.416890, -6.270770 Open point
- CN0104035FL · 53.417487, -6.278661 Open point
- CN0102519FL · 53.417768, -6.280227 Open point
- CN0101648FL · 53.417141, -6.270515 Open point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
Use the planning reference with the official register or the PlanningBrief council overview below.
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
The construction of 1 no. light industrial/warehouse and associated site development works at Unit E1 Horizon Logistics Park, off R108, at the townlands of Merryfalls & Silloge, St. Margaret's, Swords, Co. Dublin.
Floor area stated for this source: 12,578 m².
Stand alone ESB Sub Station and Switch room at Unit E Horizon Logistics Park, Harristown, St Margaret’s, Swords, Co. Dublin
Floor area stated for this source: 36 m².
Stand alone ESB Sub Station and Switch room at Unit C Horizon Logistics Park, Harristown, St Margaret’s, Swords, Co. Dublin.
Floor area stated for this source: 36 m².
Light industrial warehouse (including wholesale use) logistics building at horizon business park (known as Unit C). Harristown, St. Margaret's, Swords, Co. Dublin.
Floor area stated for this source: 6,627 m².
Light Industrial/ Warehouse (including wholesale use logistics building at Horizon Logistics Park (Known as Site E2), Harristown, St. Margaret's, Swords, Co. Dublin
Floor area stated for this source: 11,457 m².
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.