Save this project to account
Connected projectGranted

1 dwelling, Castlequarter Blakemount, Tubber, Co. Clare

Granted · Castlequarter Blakemount, Tubber, Co. Clare

Planning units1Source-stated
Planning floor area294.96 m²Source-stated; verify
Planning records1
Commencement events2
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

for the construction of a single storey dwelling house, garage, a proprietary waste water treatment system and ancillary site works

Planning authority
clarecountycouncil
Lead planning reference
2560517
Application date
25 Aug 2025
Decision date
16 Oct 2025
Project type
One-off house
Value band
€250k–500k

Exact evidence

Planning records

2560517 · Planning application

Clare County Council · CONDITIONAL · 2025-10-16

1 units · Source-stated planning-record quantity

294.96 m² · Source-stated planning-record quantity

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

CN0135203CE · 2025-11-10

The construction of a detached garage.

54 m² · Source-stated event-specific quantity

CN0135214CE · 2025-11-10

The construction of a single storey dwelling house, a proprietary waste water treatment system and ancillary site works

1 units · Source-stated event-specific quantity
245 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.