Save this project to account
Connected projectGranted

~1 dwelling, Doirin, 16 Bishopstown Avenue, Model Farm Road

Granted · Doirin, 16 Bishopstown Avenue, Model Farm Road

Planning units~1Estimated from the surfaced classification
Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

Permission is sought for the following works to an existing two-storey dwelling house: the retention of an existing domestic garage conversion and adjoining single-storey rear extension, the demolition of existing single-storey rear extensions, the construction of single-storey rear extensions, the installation of 10 no. roof windows in total on existing and proposed single-storey roofs, alterations to the existing side (north) elevation, alterations to the existing vehicular entrance, the demolition of agraden shed and construction of a new garden shed, and all associated site works.

Planning authority
corkcitycouncil
Lead planning reference
2543829
Application date
23 Apr 2025
Decision date
17 Jun 2025
Project type
One-off house

Exact evidence

Planning records

25/43829 · Planning application

Cork City Council · CONDITIONAL · 2025-06-17

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

CN0136584CY · 2025-12-15

works to an existing two-storey dwelling house: the construction of single-storey rear extensions, the installation of 10 no. roof windows in total on existing and proposed single-storey roofs, alterations to the existing side (north) elevation, alterations to the existing vehicular entrance.

1 units · Source-stated event-specific quantity
252 m² · Source-stated event-specific quantity

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.