Save this project to account
Connected projectGranted

~1 dwelling, BALLYNAKILLY, CHURCHILL, LETTERKENNY PO

Granted · BALLYNAKILLY, CHURCHILL, LETTERKENNY PO

Planning units~1Estimated from the surfaced classification
Planning records1
Commencement events1
Appeals0
Completion evidence0

Qualified scale is available from the current public evidence. Planning and event-specific quantities remain separate below.

Planning lead

Current planning presentation

(1) REFURBISHMENT OF EXISTING DERELICT DWELLING HOUSE, TO INCLUDE PARTIAL DEMOLITION OF EXISTING DWELLING HOUSE AND ALTERATIONS TO EXISTING ELEVATIONS, (2) CONSTRUCTION OF FRONT AND SIDE EXTENSIONS TO ABOVE MENTIONED EXISTING DWELLING HOUSE, (3) INSTALLATION OF NEW WASTEWATER TREATMENT SYSTEM AND (4) ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS

Planning authority
donegalcountycouncil
Lead planning reference
2560827
Application date
23 May 2025
Decision date
3 Jul 2025
Project type
One-off house

Exact evidence

Planning records

25/60827 · Planning application

Donegal County Council · CONDITIONAL · 2025-07-03

Open official record

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Building control evidence

Separate commencement events

CN0135263DL · 2025-11-05

Commencement evidence is linked; rejected quantities remain only in the sealed source artifact.

No publishable event quantity stated

Source-stated quantities are withheld because source records conflict.

Planning-case scale and each commencement-event quantity remain separate; notice quantities are never added into a project total.

Appeal evidence

Appeals

No appeal event is linked.

Completion evidence

Completion records

No completion evidence is linked.