GrantedDecision recorded

Commercial fit-out, Unit 1, Apex Hub, at Calmount Road and Ballymount Avenue...

Dublin 12, Dublin · South Dublin County Council · Plan SD25A/0310W · PB ref PB-10000402519

Planning permission is sought for the following alterations: • Internal alterations at the ground floor level of the permitted warehouse/logistics unit, including a change of use of 310 sq.m, to provide additional ancillary staff welfare facilities and ancillary office accommodation; • Provision of an additional 158 sq.m at...

Indicative value €250k–500k PB indicative band
Units applied for Not listed public application record
Floor area 468 m² published reliable figure
Decision 16 Feb 2026 public planning date
Commenced 21 May 2026 public commencement index
Decision-stage scope

The public decision state is shown, but conditions and later amendments can still change delivery scope.

Application scope

Package signals below are limited to wording in the public application record.

Not procurement evidence

No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.

Opportunity & supplier intelligence

What is known, and what may happen next

Source-linked

Timing is a planning-stage outlook, not a tender, award, contractor appointment, supplier appointment or guaranteed procurement date.

Likely procurement timing Site activity evidenced

A linked public commencement record can signal site-stage demand. It does not confirm that any package remains unawarded or publish a procurement date.

21 May 2026 / CN0142435SD / Confidence: Medium
Decision GRANT PERMISSION & GRANT RETENTION

Decision date 16 Feb 2026.

Open evidence
Commencement activity Official activity indexed

21 May 2026 / CN0142435SD

High for recorded activity
Drawings availability Drawing availability not indexed

No drawing entry is available in this lead's bounded document evidence.

Source limited

Confirmed application scope

Planning permission is sought for the following alterations: • Internal alterations at the ground floor level of the permitted warehouse/logistics unit, including a change of use of 310 sq.m, to provide additional ancillary staff welfare facilities and ancillary office accommodation; • Provision of an additional 158 sq.m at first floor level for ancillary office accommodation; • Amendments to façade treatment including signage and louvres; • Repositioning of the roof mounted Solar PVs; • Other associated...

Ref SD25A/0310W Source-linked Official application description for exact planning reference SD25A/0310W
Open scope evidence

Public source roles

No named firm role is published in this panel's source contract. PlanningBrief does not infer a contractor or supplier.

Explicit source signals only

1 package
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

SD25A/0310W Explicit description / Source-linked Source
Confidence & provenance 1 official source
Authority
South Dublin County Council
Exact reference
SD25A/0310W
Evidence reviewed
2 Jun 2026
Confidence
Source-linked

Facts come from the indexed public planning record and any bounded structured document evidence. No request-time official fetch, tender, award or appointment inference is used.

Application-stage scope

What the public record evidences

2 source-supported signals
Commercial fit-out

Commercial fit-out

The public application record identifies commercial fit-out in the submitted planning scope.

SD25A/0310WExplicit application record
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

SD25A/0310WExplicit description signal

Only source-supported scope signals are shown; generic trade padding is omitted.

Project facts

Named source parties

Promoter
not included in reference feed
Planning agent
not included in reference feed
Official description

Application text

Planning permission is sought for the following alterations: • Internal alterations at the ground floor level of the permitted warehouse/logistics unit, including a change of use of 310 sq.m, to provide additional ancillary staff welfare facilities and ancillary office accommodation; • Provision of an additional 158 sq.m at first floor level for ancillary office accommodation; • Amendments to façade treatment including signage and louvres; • Repositioning of the roof mounted Solar PVs; • Other associated alterations including to the landscaped areas; and • All associated development works Retention permission is sought for the following: • Reconfiguration of car parking layout, including amendments to circulation arrangements adjacent to the building entrance. No change is proposed to the overall number of car parking spaces; • Repositioning of the bicycle shelters; • Amendments to façade treatment, including: o Reconfiguration of glazing mullion centres and incorporation of additional opening sections; o Provision of a first-floor opening vent window to Staircore 2; o Minor adjustments to the cladding arrangement at parapet level; • Repositioning of the roof mounted AOVs; and • All associated site development works. The proposed alterations result in an overall increase of 158 sq.m in the total GFA of the warehouse/logistics unit from 3,026 sq.m to 3,184 sq.m (including ancillary office and staff welfare facilities).

Source-aware chronology

Application to site progress

Empty lanes explain their state.
AppealsAn Coimisiún Pleanála
  1. Appeal No appeal indexed No public appeal record is indexed against this application.
CommencementPublic commencement index
  1. Commenced 21 May 2026 CN0142435SD
CompletionPublic completion projection
  1. Completed Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Evidence register

Source, scope and limits

Public planning record
Application description and scale SD25A/0310W

Planning permission is sought for the following alterations: • Internal alterations at the ground floor level of the permitted warehouse/logistics unit, including a change of use of 310 sq.m, to provide additional ancillary staff welfare facilities and ancillary office accommodation; • Provision of an additional 158 sq.m at first floor level for ancillary office accommodation; • Amendments to façade treatment including signage and louvres; • Repositioning of the roof mounted Solar PVs; • Other associated alterations including to the landscaped areas; and • All associated development works Retention permission is sought for the following: • Reconfiguration of car parking layout, including amendments to circulation arrangements adjacent to the building entrance. No change is proposed to the overall number of car parking spaces; • Repositioning of the bicycle shelters; • Amendments to façade treatment, including: o Reconfiguration of glazing mullion centres and incorporation of additional opening sections; o Provision of a first-floor opening vent window to Staircore 2; o Minor adjustments to the cladding arrangement at parapet level; • Repositioning of the roof mounted AOVs; and • All associated site development works. The proposed alterations result in an overall increase of 158 sq.m in the total GFA of the warehouse/logistics unit from 3,026 sq.m to 3,184 sq.m (including ancillary office and staff welfare facilities).

AuthoritySouth Dublin County Council
ReferenceSD25A/0310W
StatusChecked 2 Jun 2026
Open official record