Commenced
6 May 2026
Commencement
Agricultural, Tinneranny, Kilkenny - Planning Application 2139
Kilkenny / Tinneranny / Tinneranny, Kilkenny
Source-linked planning record
Agricultural, Tinneranny, Kilkenny - Planning Application 2139
Kilkenny / Tinneranny / Tinneranny, Kilkenny- PB ref
- PB-294791
- Plan ref
- 2139
- Authority
- Kilkenny County Council
- Stage / date
- Commencement / 6 May 2026
- Est. value band
- Value not disclosed
- Project class
- Agricultural
- Promoter
- not available yet
- Architect / agent
- not available yet
Source: http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/2139/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Kilkenny County Council
- Application reference
- 2139
- Applicant
- not available yet
- Agent
- not available yet
- Decision stage
- Commencement
- Commenced
- 6 May 2026
Official description
Verbatim source text
for the construction of a milking parlour and dairy with ancillary underground dairy washing tank and cow handling facilities, cubicle house with ancillary underground slurry storage tank, covered feed passages, Loose animal house, silage slab, concrete apron and all associated site works including new farm entrance to public road
Verify against official sourceExplore the area
More Kilkenny planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- not available yet
- Planning agent
- not available yet
Lifecycle timeline
Application to site progress
-
Commenced
6 May 2026 Work started · Construction of agricultural shed, including slurry storage tank and handling facilities -
Completed
Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.