Final grant notified on 10 August 2026 following the council order of 1 July. February recommendations and March drawings identify design scope; no installation, commissioning or resolution of the extension interface is established.
Final grant covers one biomass enclosure and two LPG tanks
Council final grant verified · Cavan planning reference 2660235 at Bailieborough Community School
What the evidence says
The final-grant notification is dated 10 August 2026 and cites the council order of 1 July. It permits one biomass boiler enclosure and two new 2,000-litre LPG tanks, subject to seven conditions. These are plant and fuel-storage quantities, not housing units.
Cavan planning reference 2660235 at Bailieborough Community School
Why it may matter — interpretation
Interpretation: separates the planning decision date, final notification and equipment scope.
What is not established
A commencement date, completed installation and commissioning are not established.
Inspect the evidence
Bailieborough biomass installation: final grant · p.1
two new 2,000 litre LPG · Issued 2026-08-10 · Final notification dated 10 August; council order dated 1 July 2026 · Checked 2026-09-05
two new 2,000 litre LPG
The school-specific recommendation is 200 kW
Design proposal; installation not established · Bailieborough-specific recommendation in report P02 dated 26 February 2026
What the evidence says
The February Stage 1–2a report recommends a 200 kW biomass boiler supported by high-efficiency gas boilers. It also calls for replacement of the existing motor control centre, integration with the existing heating header and controls, and a new domestic hot-water cylinder.
Bailieborough-specific recommendation in report P02 dated 26 February 2026
Why it may matter — interpretation
Interpretation: identifies the actual retrofit package rather than applying the wider programme’s boiler range to this school.
What is not established
Selected boiler manufacturer, final capacity schedule, controls specification and procurement are not established.
Inspect the evidence
Bailieborough mechanical and electrical Stage 1–2a report · p.26
Implement the 200-kW biomass boiler · Issued 2026-02-26 · P02; school-specific report, separate from generic programme discussion; received 2026-05-08 · Checked 2026-09-05
Implement the 200-kW biomass boiler
The later drawing gives a larger enclosure envelope
Later application drawing; final installation unverified · March Stage 2B drawing following the February preliminary report
What the evidence says
The February report discusses a 13 m by 3.5 m enclosure. The Stage 2B drawing dated 26 March labels the proposed enclosure as 14,000 mm long, 4,100 mm wide and 4,268 mm high. It distinguishes enclosure supply by an ESCO manufacturer from the other mechanical and electrical services.
March Stage 2B drawing following the February preliminary report
Why it may matter — interpretation
Interpretation: preserves the dated dimensional revision and the stated package boundary.
What is not established
No specific ESCO supplier, contract award or as-built dimensions are established.
Inspect the evidence
Biomass enclosure layout drawing · p.1
Length / 14,000mm · Issued 2026-03-26 · Stage 2B submission; drawing (5-)M007; received 2026-05-08 · Checked 2026-09-05
Length / 14,000mm
Bailieborough mechanical and electrical Stage 1–2a report · p.26
13 m x 3.5 m · Issued 2026-02-26 · P02; school-specific report, separate from generic programme discussion; received 2026-05-08 · Checked 2026-09-05
13 m x 3.5 m
The LPG detail defines enclosure and civil requirements
Design proposal; installation not established · Stage 2B LPG detail of 26 March 2026; individual tank schematic
What the evidence says
The March schematic depicts a 3,000 mm long, 1,500 mm diameter LPG tank, at least 1 m surrounding clearance, roof netting, outward-opening gates and fencing at least 1.8 m high. It calls for a 150 mm concrete base. This single-tank schematic is not used to replace the grant’s two-tank quantity.
Stage 2B LPG detail of 26 March 2026; individual tank schematic
Why it may matter — interpretation
Interpretation: separates a repeatable tank detail from the authorised number of tanks.
What is not established
Final supplier coordination, approved installation layout and completed safety clearances are not established.
Inspect the evidence
LPG tank layout and compound drawing · p.1
1m CLEARANCE TO BE ACHIEVED · Issued 2026-03-26 · Stage 2B submission; drawing (5-)M006; received 2026-05-08 · Checked 2026-09-05
1m CLEARANCE TO BE ACHIEVED
The report flags a timing clash with extension works
Current sequencing not established · Dated February implementation caution, distinguished from the August planning grant
What the evidence says
The February report says the biomass project might not proceed as then planned because installation could interfere with the ongoing school extension. The August final grant establishes permission but does not establish that this sequencing concern was resolved.
Dated February implementation caution, distinguished from the August planning grant
Why it may matter — interpretation
Interpretation: keeps an operational dependency visible without claiming that the earlier delay remains active today.
What is not established
A coordinated installation programme, resolved interface and current works status have not been inspected.
Inspect the evidence
Bailieborough mechanical and electrical Stage 1–2a report · p.26
direct conflict with the ongoing extension works · Issued 2026-02-26 · P02; school-specific report, separate from generic programme discussion; received 2026-05-08 · Checked 2026-09-05
direct conflict with the ongoing extension works
Selected pages of 4 government-published PDFs were visually inspected. Twenty public document rows were retained. Selected pages of four PDFs were visually reviewed; the full 49-page engineering report and other file entries were not completely inspected. Proposals do not establish procurement or installed work.