Pending application received 13 August 2026. The 27 August utility observations are not a planning permission or an executed connection agreement. The proposed treatment-plant renewal also serves 34 existing neighbouring homes; those homes are not added to the new-build scope.
Two named foul pumps remain an equivalent-product proposal
Application proposal; permission, procurement and installation unverified · Proposed foul pumping package for the mixed-use application
What the evidence says
The May proposal specifies two Flygt NP3085 1.6 kW submersible pumps or similar, a precast pump sump, 25 m³ holding tank and valve chamber. Its design uses a 160 m rising main in 90 mm HDPE SDR17 at 4 l/s and 7.14 m total head. Emergency storage is approximately 31,400 litres across the sump and holding tank. Ground conditions can require an added slab or concrete surround.
Proposed foul pumping package for the mixed-use application
Why it may matter — interpretation
A pump and precast supplier should confirm hydraulic duty, ground conditions and equivalent-product acceptance before pricing.
What is not established
Selected pump, final tank design, award and installation are unknown; no duty/standby mode is inferred.
Inspect the evidence
Foul Water Pump Sump Proposal · p.4
90mm HDPE SDR17 · Issued 2026-05-25 · Pump-sump proposal dated 25 May 2026, received 13 August; catalogue upload 14 August · Checked 2026-09-06
90mm HDPE SDR17
Foul Water Pump Sump Proposal · p.5
Flygt NP3085 1.6kW · Issued 2026-05-25 · Pump-sump proposal dated 25 May 2026, received 13 August; catalogue upload 14 August · Checked 2026-09-06
Flygt NP3085 1.6kW
Central infiltration uses Aquacell or an approved equivalent
Application proposal; permission, procurement and installation unverified · Stormwater system in Galway County 2661390
What the evidence says
FL01 proposes Wavin Aquacell storage media, reference 6LB250/4064832 or a similar approved product, for a 25 m×2.5 m×2 m central infiltration trench. Some roofs feed that trench; others use smaller rear trenches. It also proposes a bypass separator and identifies NSBE010 for the calculated catchment. These are design specifications, not measured built assets.
Stormwater system in Galway County 2661390
Why it may matter — interpretation
A drainage supplier should obtain the current trench layout and equivalent-product approval before pricing storage modules and separators.
What is not established
Final approval, supplier selection, construction quantities and installation are unverified.
Inspect the evidence
Water Services and Drainage Design Report · p.14
Wavin Aquacell · Issued 2026-08-12 · FL01 final report issue 12 August 2026, following DR02 on 11 August; received 13 August. Final report issue is not final permission. · Checked 2026-09-06
Wavin Aquacell
A metered water main and hydrant network are proposed
Application proposal; permission, procurement and installation unverified · Water connection and hydrants for the proposed mixed-use development
What the evidence says
The engineer proposes a metered 150 mm supply and 150 mm Class C hydrant main. The report describes estimated water demand, not measured consumption. Uisce Éireann subsequently requests a connection agreement before commencement and prohibits building over its public assets.
Water connection and hydrants for the proposed mixed-use development
Why it may matter — interpretation
A water-services designer must coordinate the proposed main with the connection agreement and asset-separation requirements.
What is not established
The executed agreement, detailed fire-water approval and installed network are not verified.
Inspect the evidence
Water Services and Drainage Design Report · p.11
150mm diameter Class C · Issued 2026-08-12 · FL01 final report issue 12 August 2026, following DR02 on 11 August; received 13 August. Final report issue is not final permission. · Checked 2026-09-06
150mm diameter Class C
Uisce Éireann planning observations · p.3
connection agreement · Issued 2026-08-27 · Uisce Éireann issue 27 August 2026; received 27 August, catalogue upload 28 August · Checked 2026-09-06
connection agreement
The concept lighting schedule separates new and existing points
Application proposal; permission, procurement and installation unverified · Concept lighting for this application and its N67 crossing
What the evidence says
The 12 August concept schedule names Urbis Schréder AXIA variants for the proposed site lighting and AMPERA EVO for the two zebra-crossing points. The five type E entries are marked existing on the layout; they are not five new procurement units. The sheet explicitly says it is not a construction drawing.
Concept lighting for this application and its N67 crossing
Why it may matter — interpretation
A lighting designer should separate existing street lights from proposed fittings and confirm the adopted schedule before ordering.
What is not established
Final optics, accepted crossings, award and installation remain unverified.
Inspect the evidence
Electric Skyline lighting layout and luminaire schedule · p.1
AXIA 3 EVO 1 · Issued 2026-08-12 · 1343-R1 dated 12 August 2026, received 13 August; concept drawing expressly not for construction · Checked 2026-09-06
AXIA 3 EVO 1
Utility feasibility does not complete the connection process
Application proposal; permission, procurement and installation unverified · Utility review of Galway County 2661390
What the evidence says
The 27 August Uisce Éireann observations confirm that feasibility has been issued, then require the applicant to enter a connection agreement and comply with its conditions. These are utility observations on a pending application, not a final planning grant or proof of a completed connection.
Utility review of Galway County 2661390
Why it may matter — interpretation
A civil contractor should verify the signed connection agreement before treating utility access as ready for construction.
What is not established
No executed agreement, planning outcome, physical connection or procurement opening is established.
Inspect the evidence
Uisce Éireann planning observations · p.2
Confirmation of Feasibility · Issued 2026-08-27 · Uisce Éireann issue 27 August 2026; received 27 August, catalogue upload 28 August · Checked 2026-09-06
Confirmation of Feasibility
Selected pages of 4 government-published PDFs were visually inspected. Only the named supporting PDFs and declared pages were inspected for these findings; remaining catalogue entries and later compliance are not reviewed. Proposals do not establish procurement or installed work.