Planning case 2561231

Limerick City and County Council · 2561231

Latest linked evidence

Planning decision · 2026-07-30

2561231 · Conditional permission

Open official source

This page connects records for one planning case. Separate permissions, amendments and phases may belong to a wider development. A notified commencement date does not confirm that building work started.

Reviewed build intelligence

What the documents establish

Government document review

The 30 July 2026 council decision to grant 169 dwellings (145 houses and 24 apartments), a creche and associated works carries 25 conditions. Commission appeal 324563 is pending. The original life-cycle report remains an application-stage proposal; council conditions are historical decision evidence, not a final permission or proof of construction.

2 official documents inspected · Checked 2026-09-05 · Official file index

Brick and render, with window and roof alternatives

Proposed in application · Original November 2025 application envelope schedule

What the evidence says
The November 2025 life-cycle report proposes substantial brickwork with painted render, double-glazed aluminium-clad or uPVC windows, and slate or tile roof coverings. These are material categories and alternatives, not a final selected product schedule.

Why it may matter — interpretation
Interpretation: identifies facade, window and roofing packages while retaining the unresolved alternatives.

What is not established
Exact finishes, manufacturers, window systems and any later agreed substitutions are not established.

Inspect the evidence

Dromdarrig: Building Life-Cycle Report · p.10
EXTERNAL BUILDING ENVELOPE · Issued November 2025 (month only) · LRD planning application, November 2025; received 25 November 2025 · Checked 2026-09-05

EXTERNAL BUILDING ENVELOPE

Heat pumps and heat-recovery ventilation remain options

Proposed in application · Original November 2025 low-energy technology options

What the evidence says
The life-cycle report says air-to-water heat pumps and mechanical heat-recovery ventilation will be considered, while natural/passive ventilation is being evaluated. It does not establish which heating or ventilation system was finally selected.

Why it may matter — interpretation
Interpretation: distinguishes potential mechanical-services packages from selected equipment.

What is not established
No heat-pump capacity, refrigerant, ventilation unit model, installation or commissioning is established.

Inspect the evidence

Dromdarrig: Building Life-Cycle Report · p.12
will be considered · Issued November 2025 (month only) · LRD planning application, November 2025; received 25 November 2025 · Checked 2026-09-05

will be considered

Council requested Storm Tech attenuation and revised calculations

Council decision under appeal · Condition 16 in the council decision to grant, now under appeal

What the evidence says
Condition 16 of the 30 July 2026 council decision requires attenuation tanks to be revised to Storm Tech type, with details and revised surface-water calculations submitted for written agreement. Details of kiosks for alarm and messaging systems are also required.

Why it may matter — interpretation
Interpretation: a later council requirement changes the drainage design and introduces a specific system type to be resolved.

What is not established
No agreed tank layout, storage volume, supplier order, installation or condition discharge is established. This is not a final Commission decision.

Inspect the evidence

Dromdarrig 25/61231: council decision to grant with 25 conditions · p.9
Storm Tech Type · Issued 2026-07-30 · 30 July 2026 council decision; Commission appeal 324563 remains pending · Checked 2026-09-05

Storm Tech Type

Council required a revised lighting design

Council decision under appeal · Condition 17 in the council decision to grant, now under appeal

What the evidence says
Condition 17 requires a revised public-lighting design for written agreement, including an alternative proposal to lighting bollards and warm-white LED (2700 K), revised warranties, and relocation of columns beside houses 1 to 9 and 97 to 105 into open space. The original lighting proposal is therefore not treated as the final adopted design.

Why it may matter — interpretation
Interpretation: prevents the earlier lighting report from being presented as an agreed current equipment schedule.

What is not established
The wording requests an alternative but does not establish the replacement colour temperature, luminaire model, quantity, warranty or agreed revision.

Inspect the evidence

Dromdarrig 25/61231: council decision to grant with 25 conditions · p.10
a revised public lighting design · Issued 2026-07-30 · 30 July 2026 council decision; Commission appeal 324563 remains pending · Checked 2026-09-05

a revised public lighting design

Council required functional EV charging and future ducting

Council decision under appeal · Condition 15 in the council decision to grant, now under appeal

What the evidence says
Condition 15 requires functional OCPP-compliant EV charging at a minimum of 20% of communal or public parking spaces. It requires ducting or containment for the remaining public parking and private residential parking, plus engagement with a charge-point operator.

Why it may matter — interpretation
Interpretation: separates operational charger provision from parking prepared for later charging.

What is not established
The total number or rating of chargers, selected manufacturer, appointed operator and electrical connection capacity are not established.

Inspect the evidence

Dromdarrig 25/61231: council decision to grant with 25 conditions · p.9
OCPP compliant charge points · Issued 2026-07-30 · 30 July 2026 council decision; Commission appeal 324563 remains pending · Checked 2026-09-05

OCPP compliant charge points

Two 110 mm telecom ducts and shared access

Council decision under appeal · Condition 20 in the council decision to grant, now under appeal

What the evidence says
Condition 20 requires drawings showing at least two 110 mm telecom ducts from the public road to each house and to multi-dwelling plant rooms. Chambers are required at ends, road crossings and changes of direction, and at intervals no greater than 250 m. Infrastructure is to be open access.

Why it may matter — interpretation
Interpretation: identifies a defined communications ducting and chamber package before construction.

What is not established
Named operators in the consultation requirement are not treated as appointed contractors. Duct lengths, chamber quantities, installed networks and final drawings remain unconfirmed.

Inspect the evidence

Dromdarrig 25/61231: council decision to grant with 25 conditions · p.12
110mm diameter telecom ducting · Issued 2026-07-30 · 30 July 2026 council decision; Commission appeal 324563 remains pending · Checked 2026-09-05

110mm diameter telecom ducting
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. Four PDFs were inspected on selected pages: a 17-page life-cycle report, 26-page lighting report, four-page significant-information notice pack and 15-page council decision. Two text-bearing PDFs support these six published-candidate facts. The lighting design is an earlier proposal superseded by a requirement for revision; the four-page notice pack is not the complete technical further-information response. Proposals do not establish procurement or installed work.

Source history

Timeline

  1. Planning application received

    2561231

    Official source

  2. Planning decision

    2561231

    Conditional permission

    Official source

What this record establishes

Only exact linked records appear here. A missing appeal, commencement or completion entry means that evidence has not been established on this page. It does not prove that the event never happened.

Planning scale and individual notice or phase quantities remain separate. Notice quantities are not added into a development total or completion percentage.