- Stage / date
- Commencement / 3 Oct 2022
- Est. value band
- €10m–30m
- Units / floor
- 94 / 9,400 m²
- Project class
- Large residential
- Promoter
- not available yet
- Architect / agent
- Woodfort Contracting Ltd
Source: http://www.eplanning.ie/LaoisCC/AppFileRefDetails/19727/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Laois County Council
- Application reference
- 19727
- Applicant
- not available yet
- Agent
- Woodfort Contracting Ltd
- Decision stage
- Commencement
- Commenced
- 3 Oct 2022
- Units
- 94
- Floor area
- 9,400 m²
- Builder / developer
- Woodfort Contracting Ltd
Official description
Verbatim source text
development at Summerhill, Portlaoise, Co. Laois on a site measuring c.3.594 Ha. The site is bounded to the north by Summerhill Lane, to the south and west by the Portlaoise Southern Circular Road and to the east by the rear gardens of dwellings along Summerhill Lane. The development will consist of 91 No. residential units (comprising 63 No. two-storey semi-detached and detached dwellings (18 No. 4 -bedroom houses, 44 No. 3 -bedroom houses and 1 No. 2-bedroom house) and 28 No. apartments provided in 2 No. three storey blocks (14 No. 1 bedroom apartments and 14 No. 3 bedroom apartments): ancillary car-parking spaces; cycle parking, pedestrian accesses, hard and soft landscaping, bin storage, boundary treatments, sub-station, solar panels, and all associated site development works above and below ground.
Verify against official sourceMore Laois planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- not available yet
- Planning agent
- Woodfort Contracting Ltd
- Builder / developer
- Woodfort Contracting Ltd
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Commenced
3 Oct 2022 Work started · phase 1 · Construction of 18 residential housing units and all associated ancillary site works -
Commenced
18 Apr 2024 Work started · phase 2 · Construction of 14 no. residential housing units and all associated ancillary site works -
Commenced
18 Apr 2024 Work started · phase 3 · Construction of units 67-74 Summerhill Development and all associated ancillary site works -
Commenced
6 Aug 2024 Work started · phase 4 · Construction of a residential block comprising two no. apartments in a terrace with a... -
Commenced
20 Dec 2024 Work started · phase 5 · Construction of three duplex apartment blocks each containing two units and all... -
Completed
Completion certificate recorded CC00000049549LS · recorded in Oct 2022 · 18 units on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026. -
Completed
Completion certificate recorded CC00000058355LS · recorded in Apr 2024 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026. -
Completed
Completion certificate recorded CC00000059059LS · recorded in Apr 2024 · 8 units on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 15 Sep 2026.