Change of use
03 Dec 2021 · Commenced
1 unique event
Dublin, Dublin · Dun Laoghaire Rathdown County Council · Planning ref D20A/0324
the development consists of the change of use of the 3rd level of Dun Laoghaire Shopping Centre from "Vacant Former Retail" to Primary Care Centre use. This involves the re- configuration of a floor area of 4,038 sq m at level 3 and includes; 1,820 sq. m. of HSE medical consulting and treatment rooms; 1,4233 ancillary office space; 815 sq. m General Practitioner Surgery facility; circulation and staff areas; new fenestration to George's Street and Marine Road at the third level; 52 new cycle parking spaces and the re- allocation of 70 existing car spaces
Reconciled event scale
5,858 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Planning ref indexed
Builder named on notice
Glenbeigh Construction Ltd
New build
20 Nov 2021 · Latest notice
3 unique events
Knocklong, Limerick · Limerick City and County Council · Planning ref 19-1184
Construction of pair of semi-detached retirement houses at Nos. 5 & 6 Maypole Crescent, Knocklong, Co. Limerick.
Unique event Works stated Scale Commenced
CN0083758LL BCMS owner-supplied export
Construction of detached retirement house at No. 7 Maypole Crescent, Knocklong, Co. Limerick.
74.5 m²Builder named
20 Nov 2021
CN0075413LL BCMS owner-supplied export
Construction of pair of semi-detached retirement houses at Nos. 5 & 6 Maypole Crescent, Knocklong, Co. Limerick.
149 m²Builder named
08 May 2021
CN0075261LL BCMS owner-supplied export
Construction of pair of semi-detached retirement houses at Nos. 3 & 4 Maypole Crescent, Knocklong, Co. Limerick.
136.5 m²Builder named
05 May 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
Material alteration Change of use
04 Nov 2021 · Commenced
1 unique event
Midleton, Cork · Cork County Council · Planning ref 204811
The refurbishment, Modification and Change of Use of Existing Warehouse Buildings (Buildings 19, 20, 21) to form part of the Jameson Experience at the Jameson Experience Heritage Centre.
New build
18 Sep 2021 · Latest notice
6 unique events
Mallow, Cork · Cork County Council · Planning ref 1255010
Construction of a new 6-storey dryer building housing a new spray dryer unit and construction of new floors within the existing Evaporator building for a new evaporator unit.
Reconciled event scale
2 units · 5,906 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Planning ref indexed
Builder not named
Unique event Works stated Scale Commenced
CN0081024CC BCMS open-data feed
Construction of a new 6-storey reinforced concrete frame Evaporator building
958 m²Builder not named
18 Sep 2021
CN0049725CC BCMS owner-supplied export
Construction of a new 6-storey dryer building housing a new spray dryer unit and construction of new floors within the existing Evaporator building for a new evaporator unit.
5,906 m²Builder not named
26 Mar 2019
CN0013301CC BCMS owner-supplied export
Material alterations and modifications to existing Silo Building
Scale not statedBuilder not named
26 Jan 2016
CN0013299CC BCMS open-data feed
New single storey Water Treatment Building
Scale not statedBuilder not named
26 Jan 2016
CN0003767CC BCMS owner-supplied export
Construction of building incorporating a 6-storey high spray dryer unit housing 2 no. dryers, evaporator unit, milk powder storage, packing and palletising, construction of weighbridge control building, construction of transformer building, construction of utility building no. 2.
Scale not statedBuilder not named
28 Nov 2014
CN0001387CC BCMS open-data feed
Redevelopment of Dairygold Co-Op Society Ltd milk powder processing facility, Mallow, Co. Cork. Phase 2 including Pasteurisation and Separation Building and Bund 31.
2 unitsBuilder not named
30 Jul 2014
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
Multi-unit residential
13 Sep 2021 · Latest notice
2 unique events
Youghal, Cork · Cork County Council · Planning ref 17/05916
Construction of 8no. dwelling units, access road, boundary walls, connection to existing services and all necessary ancillary site works. This notice covers houses No. 8-15 and is Phase 2 of a 2 phase development of 15no units in total.
Reconciled event scale
803.5 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Planning ref indexed
Builder not named
Unique event Works stated Scale Commenced
CN0080848CC BCMS owner-supplied export
Construction of 8no. dwelling units, access road, boundary walls, connection to existing services and all necessary ancillary site works. This notice covers houses No. 8-15 and is Phase 2 of a 2 phase development of 15no units in total.
Scale not statedBuilder not named
13 Sep 2021
CN0077712CC BCMS owner-supplied export
Construction of 7no. dwelling units, access road, boundary walls, connection to existing services and all necessary ancillary site works. This notice covers houses No. 1-7 and is Phase 1 of a 2 phase development of 15no units in total.
803.5 m²Builder not named
22 Jun 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
23 Aug 2021 · Latest notice
3 unique events
Mullingar, Westmeath · Westmeath County Council · Planning ref 17/6126
Construction of 4 no dwelling houses, nos. 79 to 82 inclusive, Ardmore Hills, Ardmore road, Mullingar, Co. Westmeath.
Unique event Works stated Scale Commenced
CN0080216WH BCMS owner-supplied export
Construction of 4 no dwelling houses, nos. 79 to 82 inclusive, Ardmore Hills, Ardmore road, Mullingar, Co. Westmeath.
850 m²Builder named
23 Aug 2021
CN0071399WH BCMS owner-supplied export
construction of 2 no new dwellings and ancillary works, nos 83 and 84 Ardmore hills, Ardmore rd, Mullingar.
451 m²Builder named
09 Dec 2020
CN0051933WH BCMS owner-supplied export
Construction of 4 No. detached dwellings, numbers 85-88 inclusive Ardmore Hills, Ardmore road, Mullingar, Co. Westmeath.
952.7 m²Builder named
27 May 2019
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
19 Aug 2021 · Commenced
1 unique event
Wexford, Wexford · Wexford County Council · Planning ref 20200660
New warehouse and office development and all associated site development works all at Drinagh, Wexford
New build
12 Aug 2021 · Commenced
1 unique event
Piercetown, Meath · Meath County Council · Planning ref 21/677
New Biopharmaceutical Manufacturing And Research Facility
Change of use
26 Jul 2021 · Commenced
1 unique event
Dublin, Dublin · South Dublin County Council
Works to existing smoke vents at Block 3A, Tallaght Cross West, Belgard Square West Tallaght, Dublin 24 as detailed in Condition 7 of Fire Certificate Grant FSC/761/19.
Reconciled event scale
511 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref not indexed
Builder named on notice
Fire Design Solutions Ltd
New build
09 Jul 2021 · Latest notice
2 unique events
Portmagee, Kerry · Kerry County Council · Planning ref 19/588
Geodome Construction(3 unit)
Reconciled event scale
320 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder named on notice
Portmagee Distilling and Brewing Company Ltd
Unique event Works stated Scale Commenced
CN0078475KY BCMS owner-supplied export
Geodome Construction(3 unit)
320 m²Builder named
09 Jul 2021
CN0078472KY BCMS owner-supplied export
Renovation of existing farm building to create visitor centre and micro distillery
190 m²Builder named
09 Jul 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
05 Jul 2021 · Latest notice
3 unique events
Galway, Galway · Galway City Council · Planning ref 2114
Construction of 2 no. detached two storey dwelling houses and all associated works.
Unique event Works stated Scale Commenced
CN0078275GY BCMS owner-supplied export
Construction of 2 no. detached two storey dwelling houses and all associated works.
418 m²Builder named
05 Jul 2021
CN0077993GY BCMS owner-supplied export
Construction of domestic garage 16 sq.m
16 m²Builder named
29 Jun 2021
CN0077992GY BCMS owner-supplied export
Construction of domestic garage 24sq.m
24 m²Builder named
29 Jun 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
Material alteration
01 Jul 2021 · Commenced
1 unique event
Dublin, Dublin · Dublin City Council · Planning ref 3435/20
Replacement of existing Asbestos Roofing Panels with new Metal decking units and installation of Photo Voltaic over part of this new roofing.
Change of use
07 Jun 2021 · Commenced
1 unique event
Cloneygowan, Offaly · Offaly County Council
Proposed 2 no. apartments on ground floor and completion of 4 no. apartments on first floor at Cloneygowan, Co. Offaly
Reconciled event scale
370 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref not indexed
Builder named on notice
Shandra Lane Construction Ltd
New build
01 Jun 2021 · Commenced
1 unique event
Ennistymon, Clare · Clare County Council · Planning ref 17603
The Demolition of the existing single storey Scoil Mhuire Post Primary School Buildings & the existing two storey Scoil Mhainchín Primary School Buildings; Construction of new 3-storey Post Primary School with connected Sports Hall, 2-storey Primary School, new internal road with set-down areas for buses and cars, ESB substation, switch room, ancillary store rooms, boiler house, car parking, ball courts, landscaping and associated site works;New site entrance from Lahinch Road and new boundary treatment;New vehicular traffic lane and associated road works at the junction of proposed site entrance and Lahinch Road
New build
27 Apr 2021 · Latest notice
2 unique events
Kildangan, Kildare · Kildare County Council · Planning ref 20509
Houses 15 + 16 Harristown Drive, Kildangan
Unique event Works stated Scale Commenced
CN0074608KE BCMS owner-supplied export
Houses 15 + 16 Harristown Drive, Kildangan
222 m²Builder named
27 Apr 2021
CN0073663KE BCMS open-data feed
Construct 6 No semi-detached bungalows on sites 9 to 14 Harristown Drive, Kildangan
6 units · 736.2 m²Builder not named
06 Apr 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
22 Apr 2021 · Latest notice
2 unique events
castletroy, Limerick · Limerick City and County Council · Planning ref 18/7010
Construction of 3 no dwellings including ancillary site works, numbers 13 to 15 (inclusive) Kylemore, Kylemore schoolhouse road, Castletroy, Co. Limerick.
Unique event Works stated Scale Commenced
CN0074323LL BCMS open-data feed
Construction of 6 new dwellngs and ancillary site works, nos. 10 to 12 (inclusive) Kylemore, and nos. 16 to 18 (inclusive) Kylemore, Kylemore schoolhouse road, Castletroy, Limerick.
6 units · 964 m²Builder not named
22 Apr 2021
CN0073997LL BCMS owner-supplied export
Construction of 3 no dwellings including ancillary site works, numbers 13 to 15 (inclusive) Kylemore, Kylemore schoolhouse road, Castletroy, Co. Limerick.
386 m²Builder named
19 Apr 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
12 Apr 2021 · Latest notice
4 unique events
Allen, Kildare · Kildare County Council · Planning ref 18/541
Residential Development of Houses No. 9-11 at Ballintine Park, Allen, Co. Kildare
Reconciled event scale
5 units · 936 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder not named
Unique event Works stated Scale Commenced
CN0073725KE BCMS owner-supplied export
Residential Development of Houses No. 9-11 at Ballintine Park, Allen, Co. Kildare
639 m²Builder named
12 Apr 2021
CN0070051KE BCMS owner-supplied export
Residential Development of Houses 15-16 / 17-18 at Ballintine Park, Allen, Co. Kildare
480 m²Builder named
02 Nov 2020
CN0069278KE BCMS owner-supplied export
Construction of: One No. Detached, 2 Storey, 4 bedroom Dwelling House located to Site No. 13
310.9 m²Builder named
15 Oct 2020
CN0059032KE BCMS open-data feed
Residential Development of 5 Houses at Ballintine Park, Allen, Co. Kildare
5 units · 936 m²Builder not named
15 Nov 2019
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
Extension
12 Apr 2021 · Latest notice
2 unique events
Charlestown, Mayo · Mayo County Council · Planning ref P20/38
Renovation & extension of 2 no. townhouses at Ballagh St, Charlestown, Co. Mayo.
Reconciled event scale
161.3 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder named on notice
Dunleavy Building Systems Ltd
Unique event Works stated Scale Commenced
CN0073846MO BCMS owner-supplied export
Renovation & extension of 2 no. townhouses at Ballagh St, Charlestown, Co. Mayo.
161.3 m²Builder named
12 Apr 2021
CN0072852MO BCMS owner-supplied export
Renovation and extension of town house 'A' @ Ballagh St. Charlestown Co. Mayo
107 m²Builder named
12 Mar 2021
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
Material alteration
07 Apr 2021 · Commenced
1 unique event
., Dublin · Dublin City Council · Planning ref SHD0001/20 ABP-306569-20
Phase 1 Enabling works consisting of: Installation of bird control / mitigation measures including to protected structures, removal of asbestos, removal of redundant fuel tank, and survey works to facilitate demolition of the existing structures. All of the described works will not form a part of the permanent structure of the Parkgate Street Development planned to be constructed on the site. Parkgate Street Development will be a subject of a separate Commencement Notice with documentation.
Reconciled event scale
13,350 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Planning ref indexed
Builder named on notice
J Ryan Construction & Demolition
Extension
30 Mar 2021 · Commenced
1 unique event
Limerick, Limerick · Limerick City and County Council · Planning ref 181145
Construction of an extension to include a new two storey 50 bed ward block extension and a single storey 25 bed ward block. The two storey block will also contain an enclosed plantroom at roof level with escape corridor and stairwells. A new two storey entrance building will be provided incorporating a new link corridor with stairs and lifts connecting the new ward blocks to the remaining H Block, the existing canteen, services and laundry building.
New build
24 Mar 2021 · Latest notice
2 unique events
Tullow, Carlow · Carlow County Council · Planning ref 16252
Part demolish existing single storey industrial unit and relocate existing entrance to construct 4 number semi detached, two storey dwellings, 4 number entrances, connection to existing services, boundary fencing and landscaping ,extension of existing footpath and access from existing internal road way within Station Manor (PL 04 - 406) and all associated site works
Reconciled event scale
4 units · 466.3 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder named on notice
Woodlawn Developments Ltd
Unique event Works stated Scale Commenced
CN0073324CW BCMS owner-supplied export
Part demolish existing single storey industrial unit and relocate existing entrance to construct 4 number semi detached, two storey dwellings, 4 number entrances, connection to existing services, boundary fencing and landscaping ,extension of existing footpath and access from existing internal road way within Station Manor (PL 04 - 406) and all associated site works
466.3 m²Builder named
24 Mar 2021
CN0058911CW BCMS open-data feed
The demolition of single storey industrial unit and the relocation of existing entrance to construct 4 no. semi detached, two storey dwellings, 4 no. entrances, connection to existing services, boundary fencing, extension of existing footpath and access from existing internal roadway within Station Manor and all associated site works.
4 units · 466.3 m²Builder not named
11 Nov 2019
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
15 Mar 2021 · Commenced
1 unique event
Tralee, Kerry · Kerry County Council · Planning ref 19/272
Construction of a 600 pupil Post primary school at Cloonmore, Tralee with connected Sports Hall and ESB sub station, 4no. ballcourts, new internal road with set-down for buses and cars and accessing 55 no. car parking spaces and associated ancillary landscaping and siteworks including reprofiling of material on site.
Extension
02 Dec 2020 · Commenced
1 unique event
Waterford, Waterford · Waterford City and County Council · Planning ref 20544
construction of new entrance and porch to front of existing dwelling together with alterations to elevations, two extensions to rear of dwelling and all associated site works
Reconciled event scale
5,500 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder named on notice
Seanie Colfer Building Contractor
New build
27 Nov 2020 · Latest notice
2 unique events
Castlebar, Mayo · Mayo County Council · Planning ref P19/227
Phase 2 - Construction of four domestic dwelling houses, connection to existing services and all ancillary site works
Reconciled event scale
4 units · 652 m²
Reconciled unique-event maximum
Highest unconflicted unique-event figure for each metric — events are not summed.
Conflicting source value withheld
Planning ref indexed
Builder named on notice
Joe Walsh Roofing Systems & Construction
Unique event Works stated Scale Commenced
CN0070885MO BCMS owner-supplied export
Phase 2 - Construction of four domestic dwelling houses, connection to existing services and all ancillary site works
652 m²Builder named
27 Nov 2020
CN0067832MO BCMS open-data feed
Construction of four domestic dwelling houses, connection to existing services and all ancillary site works
4 units · 652 m²Builder not named
21 Sep 2020
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.
New build
12 Oct 2020 · Latest notice
3 unique events
Sneem, Kerry · Kerry County Council · Planning ref 161151
CONSTRUCTION OF TWO SEMI- DETACHED HOUSES
Unique event Works stated Scale Commenced
CN0069014KY BCMS open-data feed
Construction of 2 semi-detached houses, No. 11 & 12 Páirc Ardshellhane, Sportsfield Road, Sneem, Co. Kerry
304 m²Builder not named
12 Oct 2020
CN0063067KY BCMS owner-supplied export
CONSTRUCTION OF TWO SEMI- DETACHED HOUSES
304 m²Builder named
23 Mar 2020
CN0046719KY BCMS open-data feed
CONSTRUCTION OF TWO SEMI-DETACHED DWELLING HOUSES
2 units · 152 m²Builder not named
17 Dec 2018
Each row is one canonical commencement event. Duplicate source wrappers are consolidated, conflicting values are withheld, and event scales are not added together.