New build
16 Jun 2017 · Latest notice
5 notices · phased
Fingals, Dublin · Fingal County Council · Planning ref FW14A/0064
Development of 2 storey 92 no. bed Nursing Home (c. 3,596 sq.m.) with a sensory garden and associated 60 no. parking spaces permitted as part of planning reg. ref. FW14A/0064. This is Phase 2 of the permitted larger development.
Notice-stated scale
78 units · 3,596 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
CN0028422FL BCMS open-data feed
Residential development of 47 houses at 1 Heathfield Park, 2, 4, 6, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30, 32, 34, 36, 38, 40, 42, 44, 46 Heathfield Walk and 3, 5, 7, 9, 11, 13, 15, 17, 19, 21, 23, 25, 27, 29, 31, 33, 35, 37, 39, 41, 43, 45, 47 Heathfield View, Heathfield, Cappagh Road, Finglas, Dublin 11
47 unitsBuilder not named
16 Jun 2017
CN0025232FL BCMS open-data feed
2 No. houses at 3 Heathfield Park & 48 Heathfield Walk from Permission for a period of 5 years for amendments to part of the development previously permitted under Reg. Ref. F05A/1869/E1.
2 unitsBuilder not named
17 Mar 2017
CN0019131FL BCMS open-data feed
7 no. houses at 2, 4, 6, 8, 10, 12 & 14 Heathfield Drive from Permission for a period of 5 years for amendments to part of the development previously permitted under Reg. Ref. F05A/1869/E1. The current proposal comprises of a mixed use development with 78 No. residential units consisting of 30 no. 2 storey 3 bed semi detached House Type A, 8 no. 2 storey 3 bed semi detached House Type B, 5 no. 2 storey 3 bed mid terrace House Type C, 8 no. 2 storey 3 bed semi detached House Type D, 8 no. 2 storey 3 bed house end terrace / semi detached Type E, 8 no. 2 storey 3 bed house end terrace / semi detached Type E1, and 11 no. 2 storey 3 bed mid terrace House Type F; with 2 no. car parking spaces to be provided per each residential dwelling; this proposal is also for a 2 storey 92 no. bed nursing home facility (c. 3,596 sq.m) with a sensory garden (c. 1,951 sq.m) and associated 60 no. parking spaces located in the eastern portion of the site; a single storey crèche facility (c. 248.5 sq.m) with an outdoor play area (c. 284.5 sq.m) and associated 20 no. staff parking spaces and 13 no. drop-off spaces located in the north-eastern portion of the site; a 2 storey community and retail building (C. 1,021 sq.m) with associated 43 no. car parking spaces located adjacent to the existing site entrance. This proposal also provides for the re-alignment of Cappagh Road; site development and landscape works; with vehicular access to the site from the existing site entrance on Cappagh Road onto Heathfield Drive, and through the opening of the already constructed entrance on Cappagh Road onto Heathfield Avenue; bin storage and ancillary site development works, all on a sit of C. 5.26 Ha which is part of a larger site at Heathfield of C. 11.9 Ha, bounded generally by Avila Park and Avila Gardens to the East, Cappagh Road to the South and South West ( the subject site is located opposite St. Mary's Orthopaedic Hospital and Mater Christi Secondary School), undeveloped industrially zoned lands t
7 unitsBuilder not named
11 Aug 2016
CN0011768FL BCMS owner-supplied export
Development of 2 storey 92 no. bed Nursing Home (c. 3,596 sq.m.) with a sensory garden and associated 60 no. parking spaces permitted as part of planning reg. ref. FW14A/0064. This is Phase 2 of the permitted larger development.
78 units · 3,596 m²Builder not named
02 Nov 2015
CN0009562FL BCMS open-data feed
Permission for a period of 5 years for amendments to part of the development previously permitted under Reg. Ref. F05A/1869/E1. The current proposal comprises of a mixed use development with 78 No. residential units consisting of 30 no. 2 storey 3 bed semi detached House Type A, 8 no. 2 storey 3 bed semi detached House Type B, 5 no. 2 storey 3 bed mid terrace House Type C, 8 no. 2 storey 3 bed semi detached House Type D, 8 no. 2 storey 3 bed house end terrace / semi detached Type E, 8 no. 2 storey 3 bed house end terrace / semi detached Type E1, and 11 no. 2 storey 3 bed mid terrace House Type F; with 2 no. car parking spaces to be provided per each residential dwelling; this proposal is also for a 2 storey 92 no. bed nursing home facility (c. 3,596 sq.m) with a sensory garden (c. 1,951 sq.m) and associated 60 no. parking spaces located in the eastern portion of the site; a single storey crèche facility (c. 248.5 sq.m) with an outdoor play area (c. 284.5 sq.m) and associated 20 no. staff parking spaces and 13 no. drop-off spaces located in the north-eastern portion of the site; a 2 storey community and retail building (C. 1,021 sq.m) with associated 43 no. car parking spaces located adjacent to the existing site entrance. This proposal also provides for the re-alignment of Cappagh Road; site development and landscape works; with vehicular access to the site from the existing site entrance on Cappagh Road onto Heathfield Drive, and through the opening of the already constructed entrance on Cappagh Road onto Heathfield Avenue; bin storage and ancillary site development works, all on a sit of C. 5.26 Ha which is part of a larger site at Heathfield of C. 11.9 Ha, bounded generally by Avila Park and Avila Gardens to the East, Cappagh Road to the South and South West ( the subject site is located opposite St. Mary's Orthopaedic Hospital and Mater Christi Secondary School), undeveloped industrially zoned lands to the North of Cappagh Road, Finglas, Dublin 11. (Part of the
22 unitsBuilder not named
11 Aug 2015
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
24 Nov 2025 · Latest notice
3 notices · phased
Thomastown, Kilkenny · Kilkenny County Council · Planning ref 2360088
Site Development Works only for the future construction of 50 No. semi- detached and terraced dwellings and a block of 4 No. apartments/duplex units at Fountain Field, Cloughabrody, Thomastown, Co. Kilkenny
Notice identity Works stated Scale Commenced
CN0135747KK BCMS owner-supplied export
Construction of a 3 storey duplex building containing 2 No. ground floor apartments and 2 No. maisonettes and all associated site development works at 51-54 Fountain Field, Thomastown, Co. Kilkenny
4 units · 392 m²Builder named
24 Nov 2025
CN0119905KK BCMS open-data feed
Phase I - Construction of 50 No. semi-detached and terraced dwellings at Fountain Field, Cloughabrody, Thomastown, Co. Kilkenny
50 units · 4,773.4 m²Builder not named
30 Sep 2024
CN0119235KK BCMS owner-supplied export
Site Development Works only for the future construction of 50 No. semi- detached and terraced dwellings and a block of 4 No. apartments/duplex units at Fountain Field, Cloughabrody, Thomastown, Co. Kilkenny
50 units · 115 m²Builder named
16 Sep 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
24 Nov 2025 · Latest notice
2 notices · phased
Athlone, Westmeath · Westmeath County Council · Planning ref PL 22/484
Phase 2 Residential Development Glenatore Athlone, Construction of 12 Units over 3 number terrace blocks, with all associated service
Notice identity Works stated Scale Commenced
CN0135988WH BCMS owner-supplied export
Phase 2 Residential Development Glenatore Athlone, Construction of 12 Units over 3 number terrace blocks, with all associated service
22 units · 648 m²Builder named
24 Nov 2025
CN0127585WH BCMS owner-supplied export
Phase 1 of Residential Development Glenatore Athlone, Construction of 10 Units over 3 number terrace blocks, with all associated services
22 units · 540 m²Builder named
18 Apr 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
27 Dec 2024 · Latest notice
4 notices · phased
Bettystown, Meath · Meath County Council · Planning ref LB190215
Residential Development (Phase 1) of 10 houses at Ardmore Avenue, Bettystown, Co. Meath. Construction of 6 no. two-bed houses, 4 no. three-bed houses and all associated site development works, services and landscaping.
Notice identity Works stated Scale Commenced
SN0011908MH BCMS open-data feed
Construction of a three storey apartment building consisting of 7 no. 3-bed apartments, 3 no. two-bed apartments and 4 no. one-bed apartments. (No.s 3-6 Ardmore Stream & 14-23 Ardmore Avenue)
14 units · 1,416 m²Builder not named
27 Dec 2024
SN0011909MH BCMS open-data feed
Construction of a three storey apartment building consisting of 5 no. 3-bed apartments and 5 no. two-bed apartments (No.s 1-2 Ardmore Stream & 1-8 Ardmore Court)
10 units · 1,027 m²Builder not named
27 Dec 2024
SN0011910MH BCMS open-data feed
Construction of a two storey apartment building consisting of 2 no. two-bed apartments and 2 no. one-bed apartments.(No.s 4-7 Ardmore Park)
4 units · 337 m²Builder not named
27 Dec 2024
CN0119883MH BCMS owner-supplied export
Residential Development (Phase 1) of 10 houses at Ardmore Avenue, Bettystown, Co. Meath. Construction of 6 no. two-bed houses, 4 no. three-bed houses and all associated site development works, services and landscaping.
28 units · 994.8 m²Builder named
27 Sep 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
11 Oct 2024 · Latest notice
2 notices · phased
Midleton, Cork · Cork County Council · Planning ref 22/04298
The construction of 17 no. residential housing units and 1 no. retail/office unit , consisting of of 3 no. 1 bed units, 10 no. 2 bed units and 4 no. 3 bed units and all ancillary site works.
Notice identity Works stated Scale Commenced
NBCO:CN0120772CC NBCO historical file
The construction of 17 no. residential housing units and 1 no. retail/office unit , consisting of of 3 no. 1 bed units, 10 no. 2 bed units and 4 no. 3 bed units and all ancillary site works.
17 units · 1,500.5 m²Builder not named
11 Oct 2024
CN0120772CC BCMS owner-supplied export
The construction of 17 no. residential housing units and 1 no. retail/office unit , consisting of of 3 no. 1 bed units, 10 no. 2 bed units and 4 no. 3 bed units and all ancillary site works.
34 units · 691.9 m²Builder named
11 Oct 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
14 Aug 2024 · Latest notice
2 notices · phased
Gorey, Wexford · Wexford County Council · Planning ref LAC2102
Construction of 20 No. Houses and Associated Site Works. Phase 1 = Houses No. 1 to No. 6, inclusive. Phase 2 = Houses No. 7 to No. 20, inclusive. This Commencement Notice relates to the 6 No. Houses in Phase 1 of the Housing Development, with associated Site Works.
Notice identity Works stated Scale Commenced
CN0118811WX BCMS owner-supplied export
Construction of 20 No. Houses and Associated Site Works. Phase 1 = Houses No. 1 to No. 6, inclusive. Phase 2 = Houses No. 7 to No. 20, inclusive. This Commencement Notice relates to the 6 No. Houses in Phase 1 of the Housing Development, with associated Site Works.
20 units · 216.3 m²Builder named
14 Aug 2024
CN0118812WX BCMS owner-supplied export
Construction of 20 No. Houses and Associated Site Works. Phase 1 = Houses No. 1 to No. 6, inclusive. Phase 2 = Houses No. 7 to No. 20, inclusive. This Commencement Notice relates to the 14 No. Houses in Phase 2 of the Housing Development, with associated Site Works.
20 units · 216.3 m²Builder named
14 Aug 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Extension
31 May 2024 · Latest notice
2 notices · phased
Kilcarbery Grange, Dublin · South Dublin County Council · Planning ref LRD23A/0009
Seven number of additional apartments on Two number of floors in a Six Storey block currently under construction at Westgate Hall, Hawthorn Way, Kilcarbery Grange, Dublin 22.
Notice identity Works stated Scale Commenced
CN0115721SD BCMS owner-supplied export
Seven number of additional apartments on Two number of floors in a Six Storey block currently under construction at Eastgate Hall, Ash Walk, Kilcarbery Grange, Dublin 22.
470 units · 624 m²Builder named
31 May 2024
CN0115724SD BCMS owner-supplied export
Seven number of additional apartments on Two number of floors in a Six Storey block currently under construction at Westgate Hall, Hawthorn Way, Kilcarbery Grange, Dublin 22.
470 units · 624 m²Builder named
31 May 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
20 May 2024 · Latest notice
4 notices · phased
Lucan, Dublin · South Dublin County Council · Planning ref SDZ19A/0008
The construction of 3 No. dwellings at Nos. 1, 3 & 5 Hallwell Avenue, Adamstown, Co. Dublin.
Notice identity Works stated Scale Commenced
CN0115287SD BCMS owner-supplied export
The construction of 3 No. dwellings at Nos. 1, 3 & 5 Hallwell Avenue, Adamstown, Co. Dublin.
102 units · 345 m²Builder named
20 May 2024
CN0089415SD BCMS owner-supplied export
8 two storey apartments at ground floor and first floor level, accessed directly from external and 8 apartments at second floor level accessed via shared stairs at Tubber Lane Road, Adamstown, South Dublin
16 units · 1,673.2 m²Builder not named
11 May 2022
CN0089416SD BCMS open-data feed
12 two storey apartments at ground floor and first floor level, accessed directly from external and 12 apartments at second floor level accessed via shared stairs at Tubber Lane Road, Adamstown, South Dublin
24 units · 2,520.4 m²Builder not named
11 May 2022
CN0076256SD BCMS open-data feed
Construction of No. 10 houses at Hallwell Adamstown - Nos. 7 - 25 (Odd) Hallwell Avenue, Lucan, Co. Dublin
10 units · 1,225 m²Builder not named
19 May 2021
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
22 Apr 2024 · Latest notice
2 notices · phased
Dublin 12, Dublin · Dublin City Council · Planning ref ABP-307186-20 (DCC Planning Ref. No. 4364/19)
Site clearance and construction of Block C, including 5 no. dwelling houses together with all associated works at Walkinstown Road/Balfe Road, Dublin 12.
Notice identity Works stated Scale Commenced
CN0113940DC BCMS owner-supplied export
Site clearance and construction of Block C, including 5 no. dwelling houses together with all associated works at Walkinstown Road/Balfe Road, Dublin 12.
56 units · 600 m²Builder named
22 Apr 2024
SN0010066DC BCMS open-data feed
Site clearance and construction of Block B, including 25 no. Apartments together with all associated works at Walkinstown Road/ Balfe Road, Dublin 12.
25 units · 1,965.3 m²Builder not named
16 Apr 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Material alteration
01 Mar 2022 · Latest notice
3 notices · phased
Clonakilty, Cork · Cork County Council · Planning ref 17/00334
Replacement of Inchydoney Apartment balconies Phase 3, Blocks G and H
Notice identity Works stated Scale Commenced
CN0086448CC BCMS owner-supplied export
Replacement of Inchydoney Apartment balconies Phase 3, Blocks G and H
22 units · 40 m²Builder named
01 Mar 2022
CN0084549CC BCMS owner-supplied export
Replacement of Inchydoney Apartment balconies Phase 2, Blocks E and F
22 units · 50 m²Builder named
04 Jan 2022
CN0074925CC BCMS owner-supplied export
Replacement of Inchydoney apartment balconies Phase 1 Block D
4 units · 20 m²Builder named
27 Apr 2021
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
23 Feb 2022 · Latest notice
2 notices · phased
Dublin, Dublin · Dun Laoghaire Rathdown County Council · Planning ref D19A/0798
This Short Form Commencement Notice for a new Residential Development on the lands comprising the former Monkstown Mansion, former Tyre Centre and rear of Carrickbrennan Credit Union at Monkstown Farm and Monkstown Grove, Blackrock, County Dublin relates to enabling works only, which includes demolition of existing structures, site clearance and excavation for level formation. No permanent development will be undertaken under this short form commencement notice. The material alteration works are subject to a FSC and as such these works will be covered under a separate Commencement Notice with Documentation at a future date.
Notice identity Works stated Scale Commenced
SN0006937DR BCMS open-data feed
Development of one number three to four-storey building comprising of one number ground floor commercial unit and 30 number apartment units (12 number one bedroom units and 18 number 2 bedroom units with associated balconies/terraces), the provision of a new vehicular entrance onto Monkstown Grove, undercroft car parking for 11 number car parking spaces and 22 number surface level car parking spaces along Monkstown Grove, three number motorcycle spaces, 48 number bicycle parkings spaces, one number Electricity Supply Board Substation, plant room and refuse storage areas at ground floor level, new pedestrian access onto Monkstown Grove and Monkstown Farm. Landscaping, including provision of a roof terrace, boundary treatment, drainage and all associated site and infrastructure works necessary to facilitate the development. All on the lands comprising former Monkstown Mansions, former Tyre Centre, and rear of Carrickbrennan Credit Union, at Monkstown Farm and Monkstown Grove, Blackrock, Co. Dublin.
30 units · 3,121 m²Builder not named
23 Feb 2022
CN0085742DR BCMS owner-supplied export
This Short Form Commencement Notice for a new Residential Development on the lands comprising the former Monkstown Mansion, former Tyre Centre and rear of Carrickbrennan Credit Union at Monkstown Farm and Monkstown Grove, Blackrock, County Dublin relates to enabling works only, which includes demolition of existing structures, site clearance and excavation for level formation. No permanent development will be undertaken under this short form commencement notice. The material alteration works are subject to a FSC and as such these works will be covered under a separate Commencement Notice with Documentation at a future date.
30 unitsBuilder named
03 Feb 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
13 Dec 2021 · Latest notice
2 notices · phased
Limerick, Limerick · Limerick City and County Council · Planning ref 187040
Phase 3 Rhedogue Hill Housing . House No's 28 to 36 inclusive. Construction of 9 no dwellings and associated site works at Rhebogue Road, Limerick
Notice identity Works stated Scale Commenced
CN0084315LL BCMS owner-supplied export
Phase 3 Rhedogue Hill Housing . House No's 28 to 36 inclusive. Construction of 9 no dwellings and associated site works at Rhebogue Road, Limerick
23 units · 810 m²Builder named
13 Dec 2021
CN0069516LL BCMS open-data feed
Phase 2 Rhebogue Hill House No's 20 to 27 inclusive of Construction of 18 no semi detached houses and 8 no terraced houses and associated site works at Rhebogue Road, Limerick.
8 units · 6,899.2 m²Builder not named
21 Oct 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
06 Oct 2021 · Latest notice
4 notices · phased
Newtown, Kildare · Kildare County Council · Planning ref 18/1841
55 No. Residential Units to consist of 39 No.Dwellinghouses and 16 No. Duplex / Apartments
Notice identity Works stated Scale Commenced
CN0082016KE BCMS owner-supplied export
55 No. Residential Units to consist of 39 No.Dwellinghouses and 16 No. Duplex / Apartments
55 units · 109 m²Builder named
06 Oct 2021
CN0076450KE BCMS owner-supplied export
55 No. Residential Units to consist of 39 No. Dwellinghouses and 16 No. Duplex / Apartments
55 units · 995.5 m²Builder named
27 May 2021
CN0076333KE BCMS open-data feed
55 No. Residential Units to consist of 39 No. dwellinghouses and 16 No. Duplex / Apartments
5 units · 552.4 m²Builder not named
25 May 2021
CN0073526KE BCMS open-data feed
55 No. Residential units to consist of 39 No. dwellinghouses and 16 No. Duplex / Apartments
23 units · 2,674.9 m²Builder not named
05 Apr 2021
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Change of use
14 Aug 2020 · Latest notice
4 notices · phased
Greystones, Wicklow · Wicklow County Council · Planning ref 15/114
Demolition of the existing structures as per planning permission details, ground works and site clearance works.
Notice identity Works stated Scale Commenced
CN0067595WW BCMS owner-supplied export
Phase 4 including the change of use and alterations of the 'Bank House' and 'An Tigin' which form part of the residential development at the former La Touche Hotel, Trafalgar Road, Marine Terrace and Cliff Road, Greystones, Co. Wicklow.
142.3 m²Builder not named
14 Aug 2020
CN0045927WW BCMS owner-supplied export
Phase 3 consisting of the construction of 8 no. new houses, 5 of which form part of the existing La Touche Hotel Building and all associated site development works at the former La Touche Hotel, Trafalgar Road, Marine Terrace and Cliff Road, Greystones, Co. Wicklow.
8 units · 1,991 m²Builder not named
09 Nov 2018
CN0038243WW BCMS open-data feed
Phase 1 of the development to include demolition of existing structures and site preparation works, and construction of 18 no. new houses and all associated site works.
18 units · 3,884 m²Builder not named
25 Apr 2018
CN0028811WW BCMS owner-supplied export
Demolition of the existing structures as per planning permission details, ground works and site clearance works.
26 unitsBuilder named
26 Jun 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
14 Jun 2019 · Latest notice
2 notices · phased
Galway, Galway · Galway City Council · Planning ref 17/30
All site ground works including all site services, boundaries nad landscaping
Notice identity Works stated Scale Commenced
CN0052846GY BCMS open-data feed
Construction of 10 no two storey houses as part of phase 2 of overall development
10 units · 1,355 m²Builder not named
14 Jun 2019
CN0049969GY BCMS owner-supplied export
All site ground works including all site services, boundaries nad landscaping
35 units · 111 m²Builder named
26 Mar 2019
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
10 Dec 2018 · Latest notice
4 notices · phased
Corcaigh, Cork · Cork City Council · Planning ref 17/37288
Construction of Units 13-16, being a four unit duplex block
Notice identity Works stated Scale Commenced
CN0046565CY BCMS open-data feed
Construction of a four unit duplex block, Units 17 to 20
4 units · 476 m²Builder not named
10 Dec 2018
CN0046459CY BCMS owner-supplied export
Construction of Units 13-16, being a four unit duplex block
28 units · 476 m²Builder named
03 Dec 2018
CN0040648CY BCMS open-data feed
Construction of 21 number three storey townhouses being house numbers 6 to 12 and 21 to 34
21 units · 3,423 m²Builder not named
27 Jun 2018
CN0038737CY BCMS open-data feed
Construction of 5 of 73 dwellings and all associated site works, being Phase 1
5 units · 845 m²Builder not named
14 May 2018
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
27 Feb 2018 · Latest notice
3 notices · phased
Bettystown, Meath · Meath County Council · Planning ref SA110828
Proposed New Residential Development know as Dun Eimear, Bettystown, Co.Meath for 115 No. units (Mixed House Types) and associated access roads with ancillary site works and infrastructure.
Notice identity Works stated Scale Commenced
CN0036279MH BCMS open-data feed
Construction of No's. 1-25 Dun Eimear Close with associated access roads and all ancillary site works and infrastructure.
25 unitsBuilder not named
27 Feb 2018
CN0030179MH BCMS owner-supplied export
Proposed New Residential Development know as Dun Eimear, Bettystown, Co.Meath for 115 No. units (Mixed House Types) and associated access roads with ancillary site works and infrastructure.
115 unitsBuilder named
10 Jul 2017
CN0027299MH BCMS open-data feed
Proposed New Residential Development known as Dun Eimear, Bettystown, Co.Meath for 115 No. units (Mixed House Types) and associated access roads with ancillary site works and infrastructure.
20 unitsBuilder not named
15 May 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
22 Feb 2018 · Latest notice
4 notices · phased
Poppintree, Dublin · Dublin City Council · Planning ref 2414/16
the development consists of 106 residential units (60 no. duplex units and 46 no. houses) and all associated site- works including roads, footpaths, drainage, landscaping works and boundary treatments.
Notice identity Works stated Scale Commenced
CN0036083DC BCMS open-data feed
55-60, 61-66, 72-77 Hampton Wood Sq., 52a 52b 52c Hampton Wood Dr., 1-12 Hampton Wood Court (Balbutcher Lane). CELL 19_3x 3-storey blocks (18 units). CELL 18_1x 3-storey block (6 units) & 9x House Type B. 33 dwelling units in total.
33 unitsBuilder not named
22 Feb 2018
SN0002065DC BCMS open-data feed
Overall development of 106 residential units at St. Margaret's Road, Poppintree, Dublin 11. The subject of this Commencement Notice is Phase 3 of the overall development and comprises units 53 - 58 Hampton Wood Drive.
6 unitsBuilder not named
19 Apr 2017
SN0001817DC BCMS open-data feed
the construction consists of 106 residential units (60. no. duplex units and 46 no. houses)and all associated site works including roads, footpaths, drainage, landscaping works and boundary treatment.
6 unitsBuilder not named
22 Dec 2016
CN0022849DC BCMS owner-supplied export
the development consists of 106 residential units (60 no. duplex units and 46 no. houses) and all associated site- works including roads, footpaths, drainage, landscaping works and boundary treatments.
106 unitsBuilder named
14 Dec 2016
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
06 Dec 2017 · Latest notice
4 notices · phased
Rathfarnham, Dublin · South Dublin County Council · Planning ref SD14A/0280
30 residential Houses, landscaping, infrastructural services and all associated site works
Notice identity Works stated Scale Commenced
CN0034220SD BCMS open-data feed
30 residential Houses, landscaping, infrastructural services and all associated site works
6 unitsBuilder not named
06 Dec 2017
CN0024871SD BCMS owner-supplied export
Completion of already commenced works to single storey dwelling at 1 Odin’s Way. Works to be completed include internal fit out of utilities, services and internal walls.
1 unitBuilder named
07 Mar 2017
CN0023518SD BCMS owner-supplied export
30 residential Houses, landscaping, infrastructural services and all associated site works
30 unitsBuilder named
18 Jan 2017
CN0016719SD BCMS open-data feed
30 residential houses, landscaping, infrastructural services and all associated site works.
5 unitsBuilder not named
01 Jun 2016
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
24 Oct 2017 · Latest notice
3 notices · phased
Greenhills, Dublin · South Dublin County Council · Planning ref SD15A/0005
Houses 34-39 Wilkins Court Part of Residential development of 61 units at Limekiln Lane under planning reg. ref; SD15A/0005
Notice identity Works stated Scale Commenced
CN0032845SD BCMS owner-supplied export
Houses 34-39 Wilkins Court Part of Residential development of 61 units at Limekiln Lane under planning reg. ref; SD15A/0005
61 unitsBuilder named
24 Oct 2017
SN0002189SD BCMS open-data feed
Duplex/Apartments Units 10-21 Wilkins Court Part of Residential development of 61 units at Limekiln Lane under planning reg. ref; SD15A/0005
20 unitsBuilder not named
08 Jun 2017
CN0025329SD BCMS open-data feed
Houses 1-9 and 22-33 Wilkins Court Part of Residential development of 61 units at Limekiln Lane under planning reg. ref; SD15A/0005
21 unitsBuilder not named
22 Mar 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
23 Oct 2017 · Latest notice
3 notices · phased
Donabate, Dublin · Fingal County Council · Planning ref F11A/0173
Construction of 99 house units - Roads and Services installation only.
Notice identity Works stated Scale Commenced
CN0032904FL BCMS open-data feed
Houses 1-4 Rahillion Place & 6-10 Rahillion Park Donabate Co Dublin
9 unitsBuilder not named
23 Oct 2017
CN0024633FL BCMS open-data feed
Phase 1 - Houses 1-11 Construction of 99 Number houses
11 unitsBuilder not named
27 Feb 2017
CN0023195FL BCMS owner-supplied export
Construction of 99 house units - Roads and Services installation only.
99 unitsBuilder named
11 Jan 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
18 Oct 2017 · Latest notice
2 notices · phased
Santry, Dublin · Fingal County Council · Planning ref F15A/0054
Residential development of 30 Apartments at Northwood Green, Santry, Dublin 9. At Santry Cross and accessed from Old Ballymun Road, Dublin 9.
Notice identity Works stated Scale Commenced
CN0032687FL BCMS owner-supplied export
Residential development of 30 Apartments at Northwood Green, Santry, Dublin 9. At Santry Cross and accessed from Old Ballymun Road, Dublin 9.
30 unitsBuilder named
18 Oct 2017
CN0028123FL BCMS open-data feed
Residential development accessed from Old Ballymun Road. A total of 32 terraced houses is proposed, two and three storey in height in the following mix: 16 no. 3 bed units and 16 no. 4 bed units.
32 unitsBuilder not named
07 Jun 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
09 Oct 2017 · Latest notice
2 notices · phased
Hansfield, Dublin · Fingal County Council · Planning ref FW16A/0030
At 13-24 incl. and 78-89 incl. Barnwell Woods, the construction of 24 no. 2-storey houses in four terraces.
Notice identity Works stated Scale Commenced
CN0032451FL BCMS open-data feed
At nos. 25-38 incl. and 43-77 incl. Barnwell Woods, the construction of 49 no. houses in detached, semi-detached and terraced form. 6 no. are 3-storey, while 43 no. are 2-storey. All are of masonry construction with concrete ground floors and tiled pitched roofs.
49 unitsBuilder not named
09 Oct 2017
CN0029129FL BCMS owner-supplied export
At 13-24 incl. and 78-89 incl. Barnwell Woods, the construction of 24 no. 2-storey houses in four terraces.
24 unitsBuilder named
30 Jun 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
04 Sep 2017 · Latest notice
3 notices · phased
Gorey, Wexford · Wexford County Council · Planning ref 20161345
permission to erect 37no. two storey dwelling houses which also involves works to a protected structure (NIAH register no. 15701201), which will consist of the following; a) 9no. 4 bed detached dwellings, b) 12no. 4 bed semi- detached dwellings, c) 16no. 3 bed semi- detached units, d) part demolition, renovation and extension of the existing two-storey protected structure to include it's conversion into 3 no. 4 bed dwelling houses with associated landscaping works, e) access to the scheme from existing house scheme roadway, f) connection to the public services and attenation systems, g) ancillary works, landscaping and boundary treatments
Notice identity Works stated Scale Commenced
CN0031284WX BCMS owner-supplied export
permission to erect 37no. two storey dwelling houses which also involves works to a protected structure (NIAH register no. 15701201), which will consist of the following; a) 9no. 4 bed detached dwellings, b) 12no. 4 bed semi- detached dwellings, c) 16no. 3 bed semi- detached units, d) part demolition, renovation and extension of the existing two-storey protected structure to include it's conversion into 3 no. 4 bed dwelling houses with associated landscaping works, e) access to the scheme from existing house scheme roadway, f) connection to the public services and attenation systems, g) ancillary works, landscaping and boundary treatments
37 unitsBuilder named
04 Sep 2017
CN0029872WX BCMS open-data feed
permission to erect 37no. two storey dwelling houses which also involves works to a protected structure (NIAH register no. 15701201), which will consist of the following; a) 9no. 4 bed detached dwellings, b) 12no. 4 bed semi-detached dwellings, c) 16no. 3 bed semi-detached units, d) part demolition, renovation, and extension of the existing two storey protected structure to include its conversion into 3no. 4 bed dwelling houses with associated landscaping works, e) access to the scheme from existing housing scheme roadway, f) connection to the public services and attenuation systems, g) ancillary works, landscaping and boundary treatments.
16 unitsBuilder not named
10 Jul 2017
CN0027482WX BCMS open-data feed
permission to erect 37 no. two storey dwelling houses which also involves works to a protected structure (NIAH register no. 15701201), which will consist of the following; a) 9 no. 4 bed detached dwellings, b) 12 no. 4 bed semi-detached dwellings, c) 16 no. 3 bed semi-detached units, d) part demolition, renovation and extension of the existing two-storey protected structure to include it's conversion into 3 no. 4 bed dwelling houses with associated landscaping works, e) access to the scheme from existing house scheme roadway, f) connection to the public services and attenuation systems, g) ancillary works, landscaping and boundary treatments.
19 unitsBuilder not named
17 May 2017
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
10 Jul 2017 · Latest notice
2 notices · phased
Dublin · Dublin City Council · Planning ref 3510/15
2016144 Focus Ireland - Apartment Development at John's Lane West, Dublin 8
Notice identity Works stated Scale Commenced
CN0029335DC BCMS owner-supplied export
2016144 Focus Ireland - Apartment Development at John's Lane West, Dublin 8
31 unitsBuilder named
10 Jul 2017
CN0022088DC BCMS owner-supplied export
2016144 Enabling works- Demolition of Existing Structure, (to enable new construction to begin).
Scale not statedBuilder named
14 Nov 2016
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.