Save this project to account
New Application · decision due 12 Nov 2026Pre-decision · not yet granted

Energy, in the townlands of Ballynakill, Farranshoneen, Williamstown, Grange...

In Waterford City, Waterford · Waterford City and County Council · Plan 2660726 · PB ref PB-3071751121

for a 10-year permission for development of a district heating energy centre at a site located at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, A heat recovery plant at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford and A district heating network pipeline in the townlands of Ballynakill...

Indicative value €500k–1m PB indicative band
Units applied for Not listed public application record
Floor area 925 m² published reliable figure
Decision due 12 Nov 2026 public planning date
Commenced None indexed public commencement index
Applied for, not granted

The record describes what is sought. Nothing is permitted until the authority decision.

Application scope

Package signals below are limited to wording in the public application record.

Not procurement evidence

No tender, award, contractor appointment, supplier appointment or procurement timetable is inferred.

Opportunity & supplier intelligence

What is known, and what may happen next

Source-linked

Timing is a planning-stage outlook, not a tender, award, contractor appointment, supplier appointment or guaranteed procurement date.

Likely procurement timing Decision-dependent

The application is pre-decision. The earliest credible supplier window is after the public decision milestone on 12 Nov 2026; no procurement timetable is published.

Decision due 12 Nov 2026 / Confidence: Medium
Decision deadline 12 Nov 2026

Public planning decision due date; the authority may update it.

Open evidence
Commencement activity No linked activity indexed

No commencement indexed / A scheme cannot commence under this application before permission.

Source limited
Drawings availability Drawing availability not indexed

No drawing entry is available in this lead's bounded document evidence.

Source limited

Confirmed application scope

for a 10-year permission for development of a district heating energy centre at a site located at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, A heat recovery plant at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford and A district heating network pipeline in the townlands of Ballynakill, Farranshoneen, Williamstown, Grange Upper, Grange Lower, Ballytruckle, Kingsmeadow, Kilbarry, Pastimeknock, Lisduggan Big, Skibbereen, Ballynaneashagh, in Waterford City, Co. Waterford. The proposed...

Ref 2660726 Source-linked Official application description for exact planning reference 2660726
Open scope evidence

Public source roles

Heatgrid Ireland Ltd
Applicant / promoter on the public planning record
Application role only; current development or appointment status is not confirmed.

Explicit source signals only

2 packages
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

2660726 Explicit description / Source-linked Source
Services

Services / drainage scope

The public application description explicitly references services / drainage scope.

2660726 Explicit description / Source-linked Source
Confidence & provenance 1 official source
Authority
Waterford City and County Council
Exact reference
2660726
Evidence reviewed
26 Sep 2026
Confidence
Source-linked

Facts come from the indexed public planning record and any bounded structured document evidence. No request-time official fetch, tender, award or appointment inference is used.

Application-stage scope

What the public record evidences

3 source-supported signals
Energy

Energy

The public application record identifies energy in the submitted planning scope.

2660726Explicit application record
Site works

Roads and site-development scope

The public application description explicitly references roads and site-development scope.

2660726Explicit description signal
Services

Services / drainage scope

The public application description explicitly references services / drainage scope.

2660726Explicit description signal

Only source-supported scope signals are shown; generic trade padding is omitted.

Project facts

Named source parties

Promoter
Heatgrid Ireland Ltd
Planning agent
Katie Fleming
Agent address
MKO Tuam Road Galway
Official description

Application text

for a 10-year permission for development of a district heating energy centre at a site located at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, A heat recovery plant at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford and A district heating network pipeline in the townlands of Ballynakill, Farranshoneen, Williamstown, Grange Upper, Grange Lower, Ballytruckle, Kingsmeadow, Kilbarry, Pastimeknock, Lisduggan Big, Skibbereen, Ballynaneashagh, in Waterford City, Co. Waterford. The proposed development will consist of the following: 1. The construction of a District Heating Energy Centre at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, with a total generated capacity of up to 45 MW. The District Heating Energy Centre comprising a boiler and heat pump building (GFA 619 sq.m), an equipment and welfare building (GFA 281 sq.m), ancillary and staff welfare buildings, thermal water tanks, a 13-metre flue, dry air coolers, gas boiler units, heat pumps, staff welfare facilities, and associated drainage, water and utility service infrastructure. 2. The construction of a heat recovery plant room (GFA 24.7 sq.m) and storage tanks at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford. 3. The construction of a district heating network pipeline (c. 8804m in length) from the proposed District Heating Energy Centre building within the following roads – R680, R686, R709, R675, R710, R683, L1515, L90605, L90038, L1518, L5521, L90999, L90342, L1521, L1522 and L1523 and the provision of pipes to connect the district heating network pipeline to sites/premises. 4. The proposed development includes all associated site development and site enabling works and ancillary infrastructure. A Natura Impact Statement (NIS) has been prepared in respect of the Proposed Development.

Source-aware chronology

Application to site progress

Empty lanes explain their state.
AppealsAn Coimisiún Pleanála
  1. Appeal No appeal possible yet The application has not been decided.
CommencementPublic commencement index
  1. Commenced No commencement indexed A scheme cannot start before it is permitted.
CompletionPublic completion projection
  1. Completed Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Evidence register

Source, scope and limits

Public planning record
Application description and scale 2660726

for a 10-year permission for development of a district heating energy centre at a site located at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, A heat recovery plant at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford and A district heating network pipeline in the townlands of Ballynakill, Farranshoneen, Williamstown, Grange Upper, Grange Lower, Ballytruckle, Kingsmeadow, Kilbarry, Pastimeknock, Lisduggan Big, Skibbereen, Ballynaneashagh, in Waterford City, Co. Waterford. The proposed development will consist of the following: 1. The construction of a District Heating Energy Centre at Waterford Crystal, Ashe Road, Pastimeknock, Waterford, with a total generated capacity of up to 45 MW. The District Heating Energy Centre comprising a boiler and heat pump building (GFA 619 sq.m), an equipment and welfare building (GFA 281 sq.m), ancillary and staff welfare buildings, thermal water tanks, a 13-metre flue, dry air coolers, gas boiler units, heat pumps, staff welfare facilities, and associated drainage, water and utility service infrastructure. 2. The construction of a heat recovery plant room (GFA 24.7 sq.m) and storage tanks at Bausch & Lomb, Waterford Industrial Park, Ballynaneashagh, Waterford. 3. The construction of a district heating network pipeline (c. 8804m in length) from the proposed District Heating Energy Centre building within the following roads – R680, R686, R709, R675, R710, R683, L1515, L90605, L90038, L1518, L5521, L90999, L90342, L1521, L1522 and L1523 and the provision of pipes to connect the district heating network pipeline to sites/premises. 4. The proposed development includes all associated site development and site enabling works and ancillary infrastructure. A Natura Impact Statement (NIS) has been prepared in respect of the Proposed Development.

AuthorityWaterford City and County Council
Reference2660726
StatusChecked 26 Sep 2026
Open official record