19 Aug 2026
AppealCase due to be decided by 15-09-2026
Kilathmoy Substation, Athea Upper, Athea Co. Limerick
Limerick / Limerick City and County Council
Key facts
Lead summary
- Board case reference
- 501904
- Parties / case type
- Appeal
- Planning authority
- Limerick City and County Council
- Status / decision
- Case due to be decided by 15-09-2026
- Received
- 19 Aug 2026
- Decision
- 19 Aug 2026
- Work on site
- No site start recorded
Official description
Verbatim source text
RED III: 10 year permission for Long duration energy storage facility to include BESS compound and all associated site works. A Natura Impact Statement was submitted to the Planning authority with this application.