Extension
08 Sep 2025 · Latest notice
2 notices · phased
Sligo, Sligo · Sligo County Council · Planning ref PL 18/392 & PL 22/60012
Phase 2 of 2 - Construction of an extension (4019m2) over five storeys with connections to the existing hospital, new entrance with a covered ramp and all associated site works.
Notice identity Works stated Scale Commenced
CN0132919SO BCMS owner-supplied export
Phase 2 of 2 - Construction of an extension (4019m2) over five storeys with connections to the existing hospital, new entrance with a covered ramp and all associated site works.
4,020 m²Builder named
08 Sep 2025
CN0121580SO BCMS open-data feed
Phase 2 of 2 - Construction of an extension (4019m2) over five storeys with connections to the existing hospital, new entrance with a covered ramp and all associated site works
4,020 m²Builder not named
23 Oct 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Extension Material alteration
01 Sep 2025 · Latest notice
2 notices · phased
Tullamore, Offaly · Offaly County Council · Planning ref 22/174
The proposed development comprises the demolition and repositioning of an existing external store, and the construction of a new three-storey extension (c.2055m2) and minor internal alteration to layout of the existing building of Coláiste Choilm, O’Moore Street, Tullamore, Co. Offaly. The proposed extension provides general classrooms, specialist rooms and a two (2) class base Special Education Needs (SEN) unit and associated ancillary accommodation. The development will also include: Redevelopment of the existing car park to provide additional car and bicycle parking spaces; Alterations to the existing boundary treatments; Provision of new footpaths, an external play area, landscaping, and all associated site works and service connections required to support the development.
Notice identity Works stated Scale Commenced
SN0012970OY BCMS open-data feed
Construction of an external store with an adjoining bin store, together with associated site works. The proposed building will be single-storey and accessed directly from the outside.
63 m²Builder not named
01 Sep 2025
CN0132015OY BCMS owner-supplied export
The proposed development comprises the demolition and repositioning of an existing external store, and the construction of a new three-storey extension (c.2055m2) and minor internal alteration to layout of the existing building of Coláiste Choilm, O’Moore Street, Tullamore, Co. Offaly. The proposed extension provides general classrooms, specialist rooms and a two (2) class base Special Education Needs (SEN) unit and associated ancillary accommodation. The development will also include: Redevelopment of the existing car park to provide additional car and bicycle parking spaces; Alterations to the existing boundary treatments; Provision of new footpaths, an external play area, landscaping, and all associated site works and service connections required to support the development.
2,055 m²Builder named
12 Aug 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Material alteration
25 Aug 2025 · Commenced
1 notice · 1 source identity
Dublin, Dublin · Dublin City Council
Refurbishment of the double height ground floor reception and mezzzanine space including the lift core lobby .The internal Fit out of level 3,4 & 5 office space along with the refurbishment of the lift corelobby and landlord washrooms.
Material alteration
25 Aug 2025 · Commenced
1 notice · 1 source identity
Dublin 2, Dublin · Dublin City Council
Office fit out of a previously completed office building (CCD C & CCDC ) at College Square, Tara Street Dublin 2
New build
20 Aug 2025 · Latest notice
2 notices · phased
Cavan, Cavan · Cavan County Council · Planning ref 2560006
Erection of a fully serviced factory unit to be used as a manufacturing facility incorporating 2 storey administration and staff facility areas, connection to services, site works consisting of car parking, boundary treatment, landscaping and all ancillary and associated site works.
Notice-stated scale
9,601.5 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0012940CN BCMS open-data feed
Construction of an ESB Substation and all ancillary works.
30.5 m²Builder not named
20 Aug 2025
CN0129139CN BCMS owner-supplied export
Erection of a fully serviced factory unit to be used as a manufacturing facility incorporating 2 storey administration and staff facility areas, connection to services, site works consisting of car parking, boundary treatment, landscaping and all ancillary and associated site works.
9,601.5 m²Builder not named
27 May 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
11 Aug 2025 · Commenced
1 notice · 1 source identity
Clane, Kildare · Kildare County Council · Planning ref 2560342
Construct Houses 49 & 50 Hamilton Park Green, Clane
New build
06 Aug 2025 · Commenced
1 notice · 1 source identity
Bunratty, Clare · Clare County Council · Planning ref 2460004
2no. two storey detached dweelings and 2no. ancilary single storey garage/storage to the rear and all necessary ancillary site development works, including entrances and connections to public water main and sewers at sites 1&2.
New build
05 Jun 2026 · Latest notice
29 notices · phased
Mullingar, Westmeath · Westmeath County Council · Planning ref 21/568
New Detached Dwelling House Irishtown Type A Site 3
Notice identity Works stated Scale Commenced
CN0143175WH BCMS owner-supplied export
for House no -26 only (Construction of New Dwelling, Wastewater Treatment System and Percolation Area) EXTENSION OF DURATION FOR 16/6001: planning reference no. 11/5121 for the construction of a new housing development, consisting of 28 No. houses to be constructed in 3 phases made up of a combination of 26 No. Detached 2 Storey Houses (as per Condition no.5 of outline permission planning ref no. 11/5121) with associated services
1 unit · 243.1 m²Builder named
05 Jun 2026
CN0142398WH BCMS open-data feed
New Detached Dwelling House Type A Site 22
1 unit · 222 m²Builder not named
18 May 2026
CN0142399WH BCMS owner-supplied export
New Detached Dwelling House Type C Site 21
1 unit · 250 m²Builder not named
18 May 2026
CN0131538WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type C Site 23
1 unit · 250 m²Builder not named
31 Jul 2025
CN0128737WH BCMS owner-supplied export
Detached Dwelling House Type B Site 17
1 unit · 257 m²Builder not named
17 May 2025
CN0127979WH BCMS owner-supplied export
Detached Dwelling House Type C Site 15
1 unit · 250 m²Builder not named
05 May 2025
CN0128109WH BCMS open-data feed
Detached Dwelling House Type D Site 27
1 unit · 290 m²Builder not named
05 May 2025
CN0128110WH BCMS owner-supplied export
Detached Dwelling House Type D Site 28
1 unit · 290 m²Builder not named
05 May 2025
CN0126103WH BCMS owner-supplied export
Construction Of A Dormer Type Dwelling house
1 unit · 232.9 m²Builder not named
11 Mar 2025
CN0122348WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type A Site 3
1 unit · 222 m²Builder named
29 Nov 2024
NBCO:CN0120569WH NBCO historical file
New Detached Dwelling Type D Site 5
1 unit · 290 m²Builder not named
16 Oct 2024
CN0120569WH BCMS owner-supplied export
New Detached Dwelling Type D Site 5
1 unit · 290 m²Builder not named
16 Oct 2024
NBCO:CN0120469WH NBCO historical file
New Detached Dwelling Type D Site 12
1 unit · 290 m²Builder not named
09 Oct 2024
CN0120469WH BCMS owner-supplied export
New Detached Dwelling Type D Site 12
1 unit · 290 m²Builder not named
09 Oct 2024
CN0119766WH BCMS owner-supplied export
Detached Dwelling House at Site 14
1 unit · 250 m²Builder not named
24 Sep 2024
CN0117759WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type B Site 7
1 unit · 290 m²Builder named
12 Aug 2024
CN0117761WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type C Site 10
1 unit · 250 m²Builder named
12 Aug 2024
CN0115470WH BCMS owner-supplied export
New Detached Dwelling House Type C at Site No.1
1 unit · 150 m²Builder named
05 Jun 2024
CN0115069WH BCMS owner-supplied export
Construction of a dwelling house and all ancillary works
1 unit · 270.9 m²Builder not named
15 May 2024
CN0113501WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type C Site 10
1 unit · 250 m²Builder named
23 Apr 2024
CN0113594WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type B Site 7
1 unit · 290 m²Builder named
23 Apr 2024
CN0112705WH BCMS owner-supplied export
Proposed new dwelling house, with associated site works at Irishtown, Mullingar, Co. Westmeath
1 unit · 269 m²Builder not named
11 Apr 2024
CN0108823WH BCMS owner-supplied export
Construction Of A Dormer Type Dwelling House
1 unit · 232.9 m²Builder not named
17 Jan 2024
CN0107846WH BCMS open-data feed
New dwellinghouse, detached garage and associated site works at no. 19 Gort an Tobar, Castlemitchell, Irishtown, Mullingar, Co. Westmeath, per planning reference no. 21/568 extension of duration for planning reference no. 16/6001 permission consequence on grant of outline permission planning reference no. 11/5121 for the construction of a new housing development.
1 unit · 247.9 m²Builder not named
29 Nov 2023
CN0101751WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type A Site 3
1 unit · 222 m²Builder named
16 Jun 2023
CN0101771WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type C Site 10
1 unit · 250 m²Builder named
16 Jun 2023
CN0099991WH BCMS owner-supplied export
New Detached Dwelling House Irishtown Type A Site No.3
1 unit · 222 m²Builder named
28 Apr 2023
CN0099294WH BCMS owner-supplied export
New Detached Dwelling House Type C Site No.8
1 unit · 250 m²Builder named
05 Apr 2023
CN0094804WH BCMS owner-supplied export
Proposed Construction Of a Dormer type dwelling house
1 unit · 270.9 m²Builder not named
27 Oct 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
29 May 2026 · Latest notice
2 notices · phased
Sligo, Sligo · Sligo County Council · Planning ref Part 8 Planning
Construction of 3 no. dwellings and associated site development works at Glenview Park, Ash Lane, Sligo
Notice identity Works stated Scale Commenced
CN0142732SO BCMS owner-supplied export
New single storey plant room measuring an area of 21.3m2, and all other associated site works and services
21.3 m²Builder named
29 May 2026
CN0140829SO BCMS owner-supplied export
Construction of 3 no. dwellings and associated site development works at Glenview Park, Ash Lane, Sligo
3 units · 378 m²Builder named
15 Apr 2026
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
26 May 2026 · Latest notice
11 notices · phased
Hodson Bay, Roscommon · Roscommon County Council · Planning ref 2360204
Single storey Plant Building B
Notice identity Works stated Scale Commenced
CN0142909RN BCMS open-data feed
Single storey Yew Point Plant Building A
13.8 m²Builder not named
26 May 2026
CN0142913RN BCMS owner-supplied export
Single storey Plant Building B
13.8 m²Builder named
26 May 2026
CN0127854RN BCMS owner-supplied export
Construction of a new 2 storey guest unit cabin (unit number 01) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder named
06 May 2025
CN0127861RN BCMS open-data feed
Construction of a new 2 storey guest unit cabin (unit number 02) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder not named
06 May 2025
CN0127863RN BCMS owner-supplied export
Construction of a new 2 storey guest unit cabin (unit number 03) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder named
06 May 2025
CN0127870RN BCMS owner-supplied export
Construction of a new 2 storey guest unit cabin (unit number 04) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder named
06 May 2025
CN0127872RN BCMS owner-supplied export
Construction of a new 2 storey guest unit cabin (unit number 05) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder named
06 May 2025
CN0127753RN BCMS owner-supplied export
Proposed Vacuum Pump Station at Yew Point Eco Village. Hodson Bay Resort, Athlone.
49.8 m²Builder named
16 Apr 2025
CN0126737RN BCMS owner-supplied export
Construction of a new 2 storey guest unit cabin (unit number 14) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
64 m²Builder named
25 Mar 2025
CN0126738RN BCMS owner-supplied export
Construction of a new single storey guest accessible cabin (unit number 20) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
46 m²Builder named
25 Mar 2025
CN0126739RN BCMS owner-supplied export
Construction of a new single storey cabin (unit number 36) at Yew Point, Hodson Bay, Athlone, Co. Roscommon
38 m²Builder named
25 Mar 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
16 May 2026 · Latest notice
2 notices · phased
Rockcorry, Monaghan · Monaghan County Council · Planning ref 20/129
Phase 02 will consist of the construction of 2 no. blocks of 3 no. single storey 2 bedroom residential care units. Phase 02 will also involve construction works to ancillary internal site service road together with car- parking spaces, pedestrian circulation and amenity areas
Notice-stated scale
6 units · 837.2 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
CN0143037MN BCMS owner-supplied export
Phase 02 will consist of the construction of 2 no. blocks of 3 no. single storey 2 bedroom residential care units. Phase 02 will also involve construction works to ancillary internal site service road together with car- parking spaces, pedestrian circulation and amenity areas
6 units · 592.2 m²Builder not named
16 May 2026
CN0096025MN BCMS open-data feed
Phase 01 will consist of the alterations and rear extensions to existing terraced housing to northern boundary of site to create 4 no. single storey 2 bedroom residential care units. Phase 01 will also involve construction works to block up existing entrance to public road and create replacement entrance and ancillary internal site service road together with car-parking spaces, pedestrian circulation and amenity areas
837.2 m²Builder not named
02 Dec 2022
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
05 May 2026 · Latest notice
2 notices · phased
Limerick, Limerick · Limerick City and County Council · Planning ref 221189
The construction of Block B comprising of 8 no. apartments all in accordance with planning permission reference 221189.
Notice-stated scale
8 units · 875.2 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0014100LL BCMS open-data feed
The construction of Block B comprising of 8 no. apartments all in accordance with planning permission reference 221189.
8 units · 875.2 m²Builder not named
05 May 2026
SN0013773LL BCMS open-data feed
Demolition of an existing derelict building and the construction of Block A comprising of 6 no. apartments all in accordance with planning permission reference 221189
6 units · 664.0 m²Builder not named
20 Feb 2026
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
23 Mar 2026 · Latest notice
5 notices · phased
Ballymount Industrial Estate, Dublin 12, Dublin · South Dublin County Council · Planning ref SD22A/0099
Apex Hub Unit 2 ESB Substation, Calmount Road, Ballymount, Dublin 12 comprising the construction of a single-storey, detached ESB Substation with 1 No. adjoining switchroom including associated ancillary works.
Notice identity Works stated Scale Commenced
CN0139802SD BCMS owner-supplied export
Apex Hub Unit 2 ESB Substation, Calmount Road, Ballymount, Dublin 12 comprising the construction of a single-storey, detached ESB Substation with 1 No. adjoining switchroom including associated ancillary works.
25 m²Builder named
23 Mar 2026
CN0116532SD BCMS open-data feed
Apex Hub Unit 1, Calmount Road & Ballymount Avenue, Ballymount Industrial Estate, Dublin 12 comprising the construction of a new warehouse / logistics unit with ancillary office use over two floors & associated site development works.
3,140 m²Builder not named
27 Jun 2024
CN0109583SD BCMS open-data feed
Apex Hub Unit 1 ESB Substation, Calmount Road & Ballymount Avenue, Ballymount Industrial Estate, Dublin 12 comprising the construction of a new single-storey ESB substation & switchroom.
25 m²Builder not named
09 Feb 2024
CN0108709SD BCMS owner-supplied export
Apex Hub External Infrastructural Works, Calmount Road & Ballymount Avenue, Dublin 12 with new footpaths, shared surfaces, linemarking, cycle track; FW, SW drains & watermains; signage, lighting, utilities ducting; hard & soft landscaping.
Scale not statedBuilder named
01 Jan 2024
CN0105767SD BCMS owner-supplied export
Apex Hub Internal Infrastructural works, Calmount Road, Dublin 12 comprising new access roads, concrete footpaths, shared surfaces, cycle track; FW, SW drains & watermains; signage, lighting & utilities ducting; & hard & soft landscaping.
Scale not statedBuilder named
26 Sep 2023
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
18 Mar 2026 · Latest notice
7 notices · phased
Sixmilebridge, Clare · Clare County Council · Planning ref 18519
Detached dwelling on site No. 10, Dun na Choille, Mountivers, Sixmilebridge, Co. Clare
Notice identity Works stated Scale Commenced
CN0139635CE BCMS owner-supplied export
Detached dwelling on site No. 10, Dun na Choille, Mountivers, Sixmilebridge, Co. Clare
1 unit · 248.8 m²Builder named
18 Mar 2026
CN0112488CE BCMS owner-supplied export
Detached dwelling on Site No 9, Dun na Choille, Mountivers, Sixmilebridge, Co Clare
Scale not statedBuilder named
12 Apr 2024
CN0111837CE BCMS owner-supplied export
Detached dwelling on Site No 7, Dun na Choille, Mountivers, Sixmilebridge, Co Clare
1 unit · 248.8 m²Builder named
05 Apr 2024
CN0100421CE BCMS owner-supplied export
Detached dwelling on site no. 8 at Dún na Coille, Mountivers, Sixmilebridge, Co Clare
Scale not statedBuilder named
15 May 2023
CN0088182CE BCMS owner-supplied export
construction of detached dwelling house with ancillary site development works
1 unit · 224 m²Builder not named
26 Apr 2022
CN0084018CE BCMS owner-supplied export
Construction of a two storey dwelling and associated site works at Site No 4, Mountievers, Sixmilebridge
1 unit · 7.6 m²Builder not named
06 Dec 2021
CN0068306CE BCMS owner-supplied export
Site No.6 of 19 serviced detached dwelling houses, 2 no. new site entrances at Mountievers Sixmilebridge Co. Clare
1 unit · 234 m²Builder named
22 Sep 2020
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
05 Mar 2026 · Latest notice
2 notices · phased
Mullingar, Westmeath · Westmeath County Council · Planning ref 23134
Construction of 3 Units at College Street, Mullingar, Co. Westmeath
Notice identity Works stated Scale Commenced
SN0013825WH BCMS open-data feed
The development will consist of the construction of a three‑storey residential building comprising two individual ground‑floor apartments, each with two bedrooms, and two duplex apartments—each with three bedrooms—located on the first and second floors.
4 units · 410.6 m²Builder not named
05 Mar 2026
CN0138855WH BCMS owner-supplied export
Construction of 3 Units at College Street, Mullingar, Co. Westmeath
4 units · 375.6 m²Builder named
26 Feb 2026
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
12 Feb 2026 · Latest notice
2 notices · phased
Bunratty, Clare · Clare County Council · Planning ref 19939
Semi Detached Duplex Unit and dwelling at Bunratty West, Bunratty, Co Clare
Notice identity Works stated Scale Commenced
SN0013662CE BCMS open-data feed
Semi Detached Duplex Unit and Dwelling at Bunratty West, Co Clare
3 units · 247.9 m²Builder not named
12 Feb 2026
CN0134033CE BCMS owner-supplied export
Semi Detached Duplex Unit and dwelling at Bunratty West, Bunratty, Co Clare
3 units · 189.4 m²Builder named
30 Sep 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
09 Feb 2026 · Latest notice
3 notices · phased
Monaghan, Monaghan · Monaghan County Council · Planning ref 2460265
Construction of 1 no. three-storey residential block (Block B) comprising 5 no. own-door units (2 no. 2-bed apartments at lower ground floor level and 3 no. 3-bed duplex maisonettes over ground/access and first floor levels) at Coill Seannach, Coolshannagh, Monaghan. All units have direct external access with no shared internal corridors or stairs serving multiple dwellings.
Notice-stated scale
7 units · 721 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0013689MN BCMS open-data feed
Construction of 1 no. three-storey residential block (Block A) comprising 5 no. own-door units (2 no. 2-bed apartments at lower ground floor level and 3 no. 3-bed duplex maisonettes over ground/access and first floor levels) at Coill Seannach, Coolshannagh, Monaghan. All units have direct external access with no shared internal corridors or stairs serving multiple dwellings.
5 units · 522.0 m²Builder not named
09 Feb 2026
SN0013693MN BCMS open-data feed
Construction of 1 no. three-storey residential block (Block B) comprising 5 no. own-door units (2 no. 2-bed apartments at lower ground floor level and 3 no. 3-bed duplex maisonettes over ground/access and first floor levels) at Coill Seannach, Coolshannagh, Monaghan. All units have direct external access with no shared internal corridors or stairs serving multiple dwellings.
5 units · 517.5 m²Builder not named
09 Feb 2026
CN0136993MN BCMS open-data feed
Construction of 7 new dwellings. Works include forming a new vehicular entrance, connections to mains services including water, foul and storm, new boundary treatments and landscaping together with all associated site works, at Coolshannagh, Monaghan, Co.Monaghan. (Phase 1).
7 units · 721 m²Builder not named
30 Dec 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Extension Material alteration
18 Nov 2025 · Latest notice
3 notices · phased
Mallow, Cork · Cork County Council · Planning ref 25/4087
The subdivision of existing Dwelling into 2 No. Dwellings and the construction of a single storey extension to the rear of each Dwelling and all associated site works
Notice identity Works stated Scale Commenced
CN0135717CC BCMS owner-supplied export
The subdivision of existing Dwelling into 2 No. Dwellings and the construction of a single storey extension to the rear of each Dwelling and all associated site works
2 units · 347 m²Builder named
18 Nov 2025
CN0134954CC BCMS owner-supplied export
Construction of a single storey extension to the rear of existing Dwelling at No. 31b, Beecher Street, Mallow, Co. Cork
1 unit · 39.6 m²Builder named
24 Oct 2025
CN0134448CC BCMS owner-supplied export
Construction of a single storey extension to the rear of existing Dwelling at No. 31a, Beecher Street, Mallow, Co. Cork
1 unit · 39.6 m²Builder named
17 Oct 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
New build
22 Oct 2025 · Latest notice
2 notices · phased
Athy, Kildare · Kildare County Council · Planning ref 2585
CRECHE and apartment building at The Alder, Meadow Mill, Athy of:Phase 3 of a three phase housing development at Clonmullen & Gallowshill, Geraldine Road, Athy, Co. Kildare.
Notice-stated scale
5 units · 945 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0013328KE BCMS open-data feed
CRECHE and apartment building at The Alder, Meadow Mill, Athy of:Phase 3 of a three phase housing development at Clonmullen & Gallowshill, Geraldine Road, Athy, Co. Kildare.
5 units · 945 m²Builder not named
22 Oct 2025
CN0133789KE BCMS open-data feed
Phase 3 (TYPE H - 4 DWELLINGS) of a three phase housing development to include erection of (a) 50 residential units comprising 2 no. two storey 100m2 3 bedroom semi-detached dwelling houses (House Type F),16 no. two storey 89.5m2 2 bedroom town houses (House Type G), 3 no. two storey apartment blocks (Block I) comprising 6 no. ground floor 73.93m2 2 bedroom apartments and 6 no. first floor 49.76m2 1 bedroom apartments, 5 no. three storey duplex blocks (Block H) comprising 10 no. ground floor 73.93m2 2 bedroom apartments and 10 no. 100m2 3 bedroom duplex apartments on first and second floors to include car parking, bin stores, bicycle stores and boundary wall, (b) new site entrance off Geraldine Road with access road, cycleway and footpath (c) provide vehicular and pedestrian access to adjoining site to south west comprising 0.8453 hectares currently zoned “C” New Residential (d) all site development works associated with main access road and phase 3 of the three phase residential development including footpaths, roads, public lighting, attenuation ponds, surface water drains, foul sewer drains, water mains and all other utility services necessary to service the proposed development at Clonmullen & Gallowshill,Geraldine Road,Athy,Co. Kildare.
4 units · 392.2 m²Builder not named
26 Sep 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Extension
12 Aug 2025 · Latest notice
2 notices · phased
Limerick, Limerick · Limerick City and County Council · Planning ref 2460004
The development will consist of a change of use from former commercial/office use building to 3 No. ‘own door’ apartment dwelling units. The proposed works will include a ground floor single storey extension to the rear including all necessary building alterations and refurbishments including the removal of an existing bay window feature to reinstate the original window opening, rear balcony, the provision of rear boundary walls and gate access and all associated site development works. This development relates to a protected structure Ref. 21517323.
Notice identity Works stated Scale Commenced
CN0131888LL BCMS owner-supplied export
The development will consist of a change of use from former commercial/office use building to 3 No. ‘own door’ apartment dwelling units. The proposed works will include a ground floor single storey extension to the rear including all necessary building alterations and refurbishments including the removal of an existing bay window feature to reinstate the original window opening, rear balcony, the provision of rear boundary walls and gate access and all associated site development works. This development relates to a protected structure Ref. 21517323.
3 units · 131.0 m²Builder named
12 Aug 2025
CN0124134LL BCMS open-data feed
The development will consist of a change of use from former commercial/office use building to 3 No. ‘own door’ apartment dwelling units. The proposed works will include a ground floor single storey extension to the rear including all necessary building alterations and refurbishments including the removal of an existing bay window feature to reinstate the original window opening, rear balcony, the provision of rear boundary walls and gate access and all associated site development works. This application relates to a protected structure Ref. 21517323
3 units · 131.0 m²Builder not named
30 Dec 2024
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.
Material alteration
08 Jun 2026 · Commenced
1 notice · 1 source identity
Dublin 13, Dublin · Dublin City Council
Proposed Material Alterations from Basement Store Room to Commercial Kitchen
Material alteration
02 Jun 2026 · Commenced
1 notice · 1 source identity
Dublin 4, Dublin · Dublin City Council
Material Alterations to St. Vincent Private Hospital, Material alterations and an internal extension to the following areas of St. Vincent's Private Hospital, Merrion Road, Dublin 4: 1. Ground Floor: Conversion of the staff room/open courtyard to a new canteen. 2. First Floor: Alterations to the existing layout serving the Cath Labs and Well Woman Section. 3. Second Floor: Alterations to the existing layout to provide operating theatres and a recovery area.
Material alteration
11 May 2026 · Commenced
1 notice · 1 source identity
Blanchardstown, Dublin · Fingal County Council
Minor internal works to existing retail unit in retail park.
Material alteration
14 Apr 2026 · Commenced
1 notice · 1 source identity
Dublin, Dublin · Dublin City Council
Office Fitout to 6th floor office space to include initial site setup, construction of partitioning, glazing, finishes, mechanical and electrical services, IT/data, security systems, and furniture.
New build
07 Apr 2026 · Latest notice
3 notices · phased
Dublin, Dublin · Fingal County Council · Planning ref FW23A/0191
Unit 8 Nexus Distribution Park, Construction of a new warehouse/logistics building with ancillary offices at Nexus Distribution Park, Cherryhound Lands, Fingal
Notice-stated scale
4,772 m²
Notice-stated max
Highest notice-stated figure for each metric — notices are not summed.
Planning ref indexed
Builder not named
Notice identity Works stated Scale Commenced
SN0014000FL BCMS open-data feed
Small Amenity type single storey building consisting of a gym & yoga room and ancillary accommodation, security room and Café(shell & core)
485 m²Builder not named
07 Apr 2026
CN0135589FL BCMS owner-supplied export
A stand-alone single storey enclosure containing a Landlord switch room and ESB substation.
26 m²Builder not named
07 Nov 2025
CN0131978FL BCMS owner-supplied export
Unit 8 Nexus Distribution Park, Construction of a new warehouse/logistics building with ancillary offices at Nexus Distribution Park, Cherryhound Lands, Fingal
4,772 m²Builder not named
06 Aug 2025
The project row shows the highest notice-stated figure for each metric. Phases and notices are not added together.