← Complete commencement inventory
The works include site establishment, soft strip out, set up and
Dublin 1, Dublin · Dublin
- Commencement date
- 2026-11-11
- Planning reference
- Not indexed
- Planning authority
- Dublin City Council
- Project type
- Material alteration
- Floor area
- 144 m² · per notice; not summed
- Builder company
- Structuretone Limited
- Developer company
- Urbeo Residential Limited
- Indexed source check
- 2026-11-01T02:49:57Z
Works description
The works include site establishment, soft strip out, set up and completion of a ground floor office fit out (partitions, ceilings, M&E, finishes, joinery, glazing, furniture), followed by testing, commissioning and handover.
This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.