Back to leads
Project start

Site clearance and construction of Block A, including 31 no. Apartments and 2 No.…

Dublin / Dublin 12 / Dublin 12, Dublin

Estimated construction value €6.7m to €8.7m
Units 31
Floor area 2,795 m²
Commenced 16 Apr 2024

Key facts

Lead summary

Commenced date
16 Apr 2024
Planning permission
ABP-307186-20 (DCC Planning Ref. No. 4364/19) & ABP-310035-21 (DCC Planning Ref. No. 2161/21)
Local authority
Dublin City Council
Units
31
Floor area
2,795 m²
Estimated construction value
€6.7m to €8.7mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate

Official description

Verbatim source text

Site clearance and construction of Block A, including 31 no. Apartments and 2 No. commercial units together with all associated works at Walkinstown Road/ Balfe Road, Dublin 12.

Verify against official source

Likely trades & supplier leads

Inferred from scheme type and scale

Review source file