Back to leads
Local authority
Fingal County Council
Units
Not listed
Floor area
48 m²
Commenced
2 Sep 2026
Project start
E House-4-T224(USS04) building as part of the customer compound at the Mooretown 220kV…
Dublin / Huntstown / Huntstown, Dublin
Key facts
Lead summary
- Commenced date
- 2 Sep 2026
- Planning permission
- ABP-311528-21 ↗
- Local authority
- Fingal County Council
- Floor area
- 48 m²
Official description
Verbatim source text
E House-4-T224(USS04) building as part of the customer compound at the Mooretown 220kV substation, Huntstown, Co Dublin
Verify against official sourceLikely trades & supplier leads