Commenced
7 Sep 2026
Project start
Construction for a new control building (EirGrid building) within a new 110kV substation…
Offaly / Ballyonan / Ballyonan, Offaly
Key facts
Lead summary
- Commenced date
- 7 Sep 2026
- Planning permission
- ABP Case no. 309491
- Local authority
- Offaly County Council
- Floor area
- 403 m²
Official description
Verbatim source text
Construction for a new control building (EirGrid building) within a new 110kV substation, associated 110kV underground grid connection, cabling and associated works.