7-Day Notice - Proposed temporary development to consist of a
Finglas, Dublin · Dublin
- Commencement date
- 2018-07-11
- Planning reference
- 2992/17
- Planning authority
- Dublin City Council
- Project type
- New build
- Floor area
- 151 m² · per notice; not summed
- Indexed source check
- 2026-06-09T15:11:14Z
Works description
7-Day Notice - Proposed temporary development to consist of a standalone extension consisting of 2nr classrooms, combined area 151.09m2, access doors and associated level access, all service connections and ancillary works at the existing St. Canice's GNS,Seamus Ennis Rd. Finglas, Co Dublin.
This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.