Alterations to the existing Acute Psychiatric Unit: construction

Beaumont, Dublin · Dublin

Commencement date
2016-01-04
Planning reference
3155/13
Planning authority
Dublin City Council
Project type
Extension
Builder company
J.j. Rhatigan & Co
Indexed source check
2026-06-09T15:11:14Z

Works description

Alterations to the existing Acute Psychiatric Unit: construction of a new link corridor from the Acute Psychiatric Unit to the main hospital building, provision of set down area and turning bay, additional plantroom at first floor level, additional plant at roof level, alterations to existing internal roof terraces to provide ancillary accommodation for first floor fitout.