← Complete commencement inventory

Commencement notice (owner-supplied)

A temporary single storey prefabricated building consisting of 2

Glasnevin, Dublin · Dublin

Commencement date
2016-12-15
Planning reference
3299/16
Planning authority
Dublin City Council
Project type
New build
Units
1 unit · notice-stated
Floor area
473 m² · per notice; not summed
Builder company
Eco Modular Buildings Ltd
Indexed source check
2026-06-09T15:11:14Z

Works description

Construction of a temporary single storey prefabricated building consisting of 2 no. classrooms and all associated site works on a site of 473sqm, located to the north of the existing St. Columba’s Church Iona Rd., Glasnevin, Dublin 9 and the south of the existing St. Columba’s National School, Crawford Avenue, Glasnevin, Dublin 9

This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.

Open grouped project and every phase