New dewatering building, new ESB substation with customer meter
Tullow, Carlow · Carlow
- Commencement date
- 2022-04-20
- Planning reference
- 01.JA0010
- Planning authority
- Carlow County Council
- Project type
- New build
- Floor area
- 129 m² · per notice; not summed
- Builder company
- Electrical and Pump Services Ltd
- Indexed source check
- 2026-06-09T15:11:14Z
Works description
New dewatering building, new ESB substation with customer meter room and new MCC kiosk at the existing Tullow Wastewater Treatment Plant.