ESB substation — Carrigtohill
Carrigtohill, Cork · Cork
- Commencement date
- 2021-01-28
- Planning reference
- 2006074
- Planning authority
- Cork County Council
- Project type
- New build
- Floor area
- 24 m² · per notice; not summed
- Builder company
- John Sisk & Son (Holdings) Ltd
- Indexed source check
- 2026-06-09T15:11:14Z
Works description
Construction of ESB substation. The ESB substation including an adjacent switchroom will be 3.375m high, 7,650m long and 4.360m wide (change of location from that previously permitted under Pl.Reg.20/4090)