The development will consist of 1No.Boiler House, 1No.
Dublin, Dublin · Dublin
- Commencement date
- 2026-10-05
- Planning reference
- Not indexed
- Planning authority
- Fingal County Council
- Project type
- New build
- Floor area
- 143 m² · per notice; not summed
- Indexed source check
- 2026-09-30T02:58:29Z
Works description
The development will consist of 1No.Boiler House, 1No. Electrical & Instrumentation (E&I) kiosk, 1No. Regulator Skid, 1No. Fuel Gas PRS Skid, and 1No. Gas Analyser kiosk with all ancillary services and associated site works located to the west of the N2 at Kilshane Road, Kilshane, Finglas, Dublin 11.