Commencement notice (owner-supplied)

Renovation and fire safety improvement works to Bedford Row

Dublin 2, Dublin · Dublin

Commencement date
2020-03-02
Planning reference
2207/18
Planning authority
Dublin City Council
Project type
Material alteration
Floor area
1829 m² · per notice; not summed
Builder company
Powercomm Engineering Ltd
Indexed source check
2026-06-09T15:11:14Z

Works description

Renovation and fire safety improvement works to Bedford Row, 38kV ESB Substation

This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.