← Complete commencement inventory

Commencement notice (owner-supplied)

Samco Ltd Development- Phase 1 to include the light engineering

Adare, Limerick · Limerick

Commencement date
2019-03-22
Planning reference
15/626
Planning authority
Limerick City and County Council
Project type
New build
Floor area
3117 m² · per notice; not summed
Builder company
Martin Cussen Construction & Civil Engineering Ltd
Indexed source check
2026-06-09T15:11:14Z

Works description

Samco Ltd Development- Phase 1 to include the light engineering manufacturing plant, ground floor offices, car parking, service yard and ancillary site works at Tough, Adare, Co Limerick

This is one commencement notice, retained separately even when it belongs to a grouped project. Personal names, contacts, Eircodes and raw private addresses are not included.