- Commencement date
- 2018-11-15
- Planning reference
- 4135/17
- Planning authority
- Dublin City Council
- Project type
- New build
- Floor area
- 31 m² · per notice; not summed
- Indexed source check
- 2026-06-09T15:11:14Z
Works description
7-Day Notice - Proposed Construction of an ESB (MV) Substation and adjoining Switchroom to support the Independent Living Units (ILUs) at the site of St. Agnes Primary Care Centre, Armagh Road, Crumlin, Dublin 12.