Commencement notice group

Commencement notices — Carrigtohill

Carrigtohill, Cork

3 unique commencement events · latest notified commencement 02 Nov 2020 · planning reference supplied

Unique commencement events
3
Latest notified commencement
02 Nov 2020
Latest notice
24 m²
Planning references supplied
20/04810
Public location
Carrigtohill, Cork

Public source geography

Site location

Public site / locality
Carrigtohill, Cork
County
Cork
Approximate source location. Use the larger map if the inline map is unavailable.
Approximate source location — not an official site boundary Open larger map

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

SN0005658CC BCMS open-data feed

This 7DN relates to the construction of a prefabricted building {Prefab S15b} within the greater development that invloves the provision of additional temporary post-primary school accomodation by way of construction of prefabricated buildings on site on a defined site area with all associated site works, including provision of hard landscaping play area, entrance, set down area, car parking, boundary treatment, bicycle parking.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 24 m².

Planning reference 20/04810
SN0005656CC BCMS open-data feed

This 7DN relates to the construction of a prefabricted building {Prefab S15a} within the greater development that invloves the provision of additional temporary post-primary school accomodation by way of construction of prefabricated buildings on site on a defined site area with all associated site works, including provision of hard landscaping play area, entrance, set down area, car parking, boundary treatment, bicycle parking.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 24 m².

Planning reference 20/04810
CN0067932CC BCMS open-data feed

The projects invloves the provision of additional temporary post-primary school accomodation by way of construction of prefabricated buildings on site (split over 3 phases) on a defined site area with all associated site works, including provision of hard landscaping play area, entrance, set down area, car parking, boundary treatment, bicycle parking.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 1,323 m².

Planning reference 20/04810

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.