Commencement notice group

an existing facility at College Park — commencement notices

Dublin 15, Dublin

3 unique commencement events · latest notified commencement 23 Oct 2023 · planning reference supplied

View full project timeline

Unique commencement events
3
Latest notified commencement
23 Oct 2023
Latest notice
12,139 m²
Planning references supplied
FW22A/0300
Public location
Dublin 15, Dublin

Commencement and completion records

Planning, start and completion evidence

The certificate is linked to its commencement notice. A corresponding planning record has not yet been established from the available source evidence.

Exact planning records
Official record actions
0
Explicit planning relationships
Duplicate source rows consolidated
Exact completion events

Planning-anchored public geography

Site identity and location

Canonical public locality
Dublin 15, Dublin
County
Dublin

Notice location variants

  • the Southern end of the existing facility
  • Dublin, Dublin
  • an existing facility at College Park, Blanchardstown, Dublin 15
  • College Park, Blanchardstown, Dublin 15
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

Notice 1 Commencement notice (owner-supplied)

Construction of interconnected Lab and Warehouse extensions to existing Alexion Pharma International Operations Limited. The proposed warehouse works involve the construction of an approx. 7639m2 extension to the North and South of the existing warehouse area of the facility and the construction of additional lab accommodation (4500m2 gross internal area over multiple levels) to the West of the existing labs at the Southern end of the existing facility.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 12,139 m².

Planning reference FW22A/0300 Builder stated: Project Management Ltd Developer stated: Alexion Pharma International Operations Ltd
Notice 2 Commencement notice (owner-supplied)

AstraZeneca - Project Joyce – construction of a new single storey MV/LV building at an existing facility at College Park, Blanchardstown, Dublin 15.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 196 m².

Planning reference FW22A/0300
Notice 3 Commencement notice (owner-supplied)

AstraZeneca - Project Joyce – construction of a new 5 storey pharmaceutical manufacturing building as an extension to an existing facility at College Park, Blanchardstown, Dublin 15

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 10,315 m².

Planning reference FW22A/0300