Commencement notice group

UCD Estate — commencement notices

Dublin 4, Dublin

3 unique commencement events · latest notified commencement 08 Mar 2024 · planning reference supplied

Unique commencement events
3
Latest notified commencement
08 Mar 2024
Latest notice
10 m²
Planning references supplied
D22A/0828
Public location
Dublin 4, Dublin

Public source geography

Site location

Public site / locality
Dublin 4, Dublin
County
Dublin

Public site labels seen across the notices

  • DUBLIN, Dublin
  • UCD Estate, University College Dublin in Belfield, Dublin 4, comprised of one pump house
  • UCD Estates, University College Dublin in Belfield, Dublin 4, comprised of one pump house

Notice coordinates differ materially, so no combined point is shown. Use the per-notice location actions in the timeline.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

CN0110800DR BCMS owner-supplied export

Pump House 2, UCD Belfield, Dublin; Proposal to construct a new pump house building at UCD Estate, University College Dublin in Belfield, Dublin 4, comprised of one pump house.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 10 m².

Planning reference D22A/0828 Builder stated: Kilwex Ltd
CN0110763DR BCMS owner-supplied export

It is proposed to construct a new pump house building at UCD Estates, University College Dublin in Belfield, Dublin 4, comprised of one pump house.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 10 m².

Planning reference D22A/0828 Builder stated: Kilwex Ltd
CN0108287DR BCMS owner-supplied export

Proposals comprise sports pitches and associated infrastructure forming Phase 1 of the planned wider phased redevelopment of the UCD Sports & Student Amenities Precinct.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 60,000 m².

Planning reference D22A/0828 Builder stated: Kilwex Ltd

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.