Commencement notice group
Housing commencement notices — Dungourney
Dungourney, Cork
18 separate notices · latest notified commencement 25 Sep 2024 · planning reference supplied
- Source notices
- 18
- Latest notified commencement
- 25 Sep 2024
- Latest notice
- 3,115 m²
- Planning references supplied
- 19/04641
- Public location
- Dungourney, Cork
Public source geography
Site location
- Public site / locality
- Dungourney, Cork
- County
- Cork
Public site labels seen across the notices
- Ardglass, Cork
- Irish Distillers Limited Dungourney Facility and ancillary services
Notice coordinates differ materially, so no combined point is shown. Use the per-notice location actions in the timeline.
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Project documents
Drawings & planning documents
Use the planning reference with the official register or the PlanningBrief council overview below.
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
Construction of Whiskey Maturation Warehouse (D193/D194) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D191/D192) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D189/D190) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of a New Electrical Sub- Station building to house Electrical Panels to facilitate operation of Warehouse Storage Facility
70 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D187/D188) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D181/D182) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D179/D180) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Forklift Charging Building at Irish Distillers Limited Dungourney Facility and ancillary services. The building will be a steel framed building on a raft foundation. The plan dimensions are 15x7m with a height to the ridge of 4.7m
122 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D177/D178) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D185/D186) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D183/D184) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D171/D172) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D173/D174) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D175/D176) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D169/D170) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of a New Electrical Sub- Station building to house Electrical Panels to facilitate operation of Warehouse Storage Facility
70 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D167/D168) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
Construction of Whiskey Maturation Warehouse (D165/D166) in a development consisting of similar buildings (each containing two warehouses). Buildings have plan dimensions of 48.4m x 65m with a height to eaves of 9.575m and a ridge height of 11.69m. The structure is a double span steel portal frame on a 6.5m grid supported on pad foundations. The roof is of Kingspan KS1000RW cladding supported on steel purlins and walls are constructed in blockwork. A central separating wall divides the building into two warehouses.
3,115 m² · stated on this notice
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.