Site start

Dundalk Business Park — site start

Dundalk, Louth

1 commencement notice · start date 06 Feb 2026 · planning references given

Planning 2560222 , 2560557 · Planning application · Council file · external

Commencement notices
1
Latest start date
06 Feb 2026
Latest notice
14,137 m²
Planning references
2560222 · 2560557
Location
Dundalk Business Park, Marshes Upper, Dundalk, Louth

Location

Where the site is

Area
Dundalk, Louth
County
Louth

Addresses on the notices

  • Dundalk Business Park, Marshes Upper, Dundalk, Louth
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

Notice 1 Seven-day notice

Construction of a new building which will consistt of manufacturing / light industry/ storage building including office and staff facilities at Dundalk Business Park, Marshes Upper, Dundalk, Co. Louth.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 14,137 m².

Planning reference 2560222 Planning reference 2560557

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.