Site start
Housing site start — Ballymore Eustace
Ballymore Eustace, Kildare
5 commencement notices · latest start date 17 May 2023 · planning reference given
Planning 19/750 · Council file · external
- Commencement notices
- 5
- Latest start date
- 17 May 2023
- Latest notice
- 109 m²
- Planning reference
- 19/750
- Location
- Ballymore Eustace, Kildare
Linked records
Planning, start and completion
- Planning applications
- 1
- Links to official records
- 1
- Links between applications
- 0
- Repeat copies merged
- 1
- Completion certificates
- 21
- Open exact official planning record: 19/750 Kildare County Council · checked 2026-07-29T15:41:08+00:00
Planning 19/750 — CONDITIONAL · Decision 2020-03-27 · Final grant 2020-06-30
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2022-08 3 units stated for this certificate · One certificate representation
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2022-08 2 units stated for this certificate · One certificate representation
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2022-08 2 units stated for this certificate · One certificate representation
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2022-08 2 units stated for this certificate · One certificate representation
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2022-08 3 units stated for this certificate · One certificate representation
- Completion certificate recorded — source scope not stated Kildare County Council · commencement notice Completion certificate · First observed in the official monthly source 2023-05 1 units stated for this certificate · One certificate representation
Showing the latest 6 of 21 exact completion events.
Planning, commencement and completion remain separate exact-source events. Dated certificates are linked by their official notice reference and authority to the associated commencement history; notice quantities are never added into a project total.
Reviewed planning, commencement and document evidence
Exact project story for 19750 under Kildare County Council, retaining 5 separate commencement identities.
- Commencement identities
- 5 retained separately
- Latest group date
- 2023-05-17 not assigned across events
- Maximum on one notice
- 38 units never summed
- Reviewed index
- 124 8 exact document links
- Permitted scale
- 91 units permission record; not summed with notices
Planning and appeal references
- Planning_Application 19750 Open exact official record
Every retained commencement event
- 2021-06-10 Commencement notice 17 units on this event · 2096 m² on this event
- 2021-07-21 Commencement notice 8 units on this event · 878 m² on this event Official public source URL unavailable in the reviewed projection
- 2022-04-19 Commencement notice 38 units on this event · 4437 m² on this event
- 2022-08-19 Commencement notice 24 units on this event · 2681 m² on this event
- 2023-05-17 Commencement notice 4 units on this event · 109 m² on this event Official public source URL unavailable in the reviewed projection
Exact organisation roles
- Kildare County CouncilPlanningauthority · Exact official planning record 19750.
Explicit facts with official citations
Each statement keeps its exact reference, official title or drawing-title locator, and review state.
- Planningoutcome Planning outcome recorded as CONDITIONAL. 19750 · Official planning record — 19750 · Decision field · exactauthorityreferencerecord Open official evidence
- Permittedscale Permitted scale record states 91 residential units and 10,396 m² floor area. 19750 · Official planning record — 19750 · Residential units and floor-area fields · exactauthorityreferencerecord Open official evidence
- Sitelayout Official file index includes “02/03/2020 - Drawings Plans/Sections/Elevations - Clarification of Further Information- Site Masterplan”. 19750 · 02/03/2020 - Drawings Plans/Sections/Elevations - Clarification of Further Information- Site Masterplan · 02/03/2020 - Drawings Plans/Sections/Elevations - Clarification of Further Information- Site Masterplan · listedonexactofficialfile Open official evidence
- Phasing Official file index includes “20/12/2019 - Drawings Plans/Sections/Elevations - Phasing Plan”. 19750 · 20/12/2019 - Drawings Plans/Sections/Elevations - Phasing Plan · 20/12/2019 - Drawings Plans/Sections/Elevations - Phasing Plan · listedonexactofficialfile Open official evidence
- Architecture Official file index includes “(July20) Drawing (Naming & Numbering) - Cond 7”. 19750 · (July20) Drawing (Naming & Numbering) - Cond 7 · (July20) Drawing (Naming & Numbering) - Cond 7 · listedonexactofficialfile Open official evidence
- Engineeringanddrainage Official file index includes “02/03/2020 - Clarification of Further Information - Civil Engineering Infrastructure”. 19750 · 02/03/2020 - Clarification of Further Information - Civil Engineering Infrastructure · 02/03/2020 - Clarification of Further Information - Civil Engineering Infrastructure · listedonexactofficialfile Open official evidence
- Landscapeplayecology Official file index includes “02/03/2020 - Drawings Landscape plan - Clarification of Further Information - Masterplan”. 19750 · 02/03/2020 - Drawings Landscape plan - Clarification of Further Information - Masterplan · 02/03/2020 - Drawings Landscape plan - Clarification of Further Information - Masterplan · listedonexactofficialfile Open official evidence
- Inspectorreport Official file index includes “20/12/2019 - Planning Report”. 19750 · 20/12/2019 - Planning Report · 20/12/2019 - Planning Report · listedonexactofficialfile Open official evidence
- Decisionorder Official file index includes “(June20) Final Grant”. 19750 · (June20) Final Grant · (June20) Final Grant · listedonexactofficialfile Open official evidence
- Roadsaccesslighting Official file index includes “02/07/2019 - Site Plan_Contours & Road Levels + FFL”. 19750 · 02/07/2019 - Site Plan_Contours & Road Levels + FFL · 02/07/2019 - Site Plan_Contours & Road Levels + FFL · listedonexactofficialfile Open official evidence
- Otherreport Official file index includes “(April23) Internal Report - Environment (Cond 24)”. 19750 · (April23) Internal Report - Environment (Cond 24) · (April23) Internal Report - Environment (Cond 24) · listedonexactofficialfile Open official evidence
- Otherdrawing Official file index includes “(April23) Compliance Letter - Cond 24”. 19750 · (April23) Compliance Letter - Cond 24 · (April23) Compliance Letter - Cond 24 · listedonexactofficialfile Open official evidence
Official document index highlights
Official drawing, report and decision titles retained from an exact authority/reference inventory; the index is not asserted to reproduce the complete authority file.
- Site layout 02/03/2020 - Drawings Plans/Sections/Elevations - Clarification of Further Information- Site Masterplan Open exact official record
- Site layout 02/07/2019 - Site Masterplan 1/500 Open exact official record
- Site layout 02/07/2019 - Site Plan & Contextual Elevation - Open exact official record
- Site layout 18/02/21- compliance amended site plan cond. 1&4 Open exact official record
- Site layout 20/12/2019 - Drawings Plans/Sections/Elevations - Site Masterplan Open exact official record
- Site layout Jan 2021-Compliance cond 9 proposed site plan Open exact official record
- Phasing 20/12/2019 - Drawings Plans/Sections/Elevations - Phasing Plan Open exact official record
- Phasing Jan 2021-Compliance cond 3, proposed phasing Open exact official record
- Architecture (July20) Drawing (Naming & Numbering) - Cond 7 Open exact official record
- Architecture (March23) Compliance Drawings - Various Open exact official record
- Architecture 02/03/2020 - Drawings Site Location - Clarification of Further Information Open exact official record
- Architecture 02/07/2019 - House Type D1 - 3 Bed Semi-Detached Wide Front Open exact official record
Showing 12 of 124 reviewed index entries.
Location
Where the site is
- Area
- Ballymore Eustace, Kildare
- County
- Kildare
- Notice source points are up to 273 m apart, so no combined representative point is shown.
Source positions remain separate:
- Public notice source · 53.134501, -6.614125 Open point
- Public notice source · 53.135111, -6.614973 Open point
- Public notice source · 53.135268, -6.614950 Open point
- Public notice source · 53.135575, -6.616733 Open point
- Public notice source · 53.135955, -6.617431 Open point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
The exact official planning file is available below.
-
Official planning file Kildare County Council planning record Application details, status and decision record for 19/750. Official council planning portal Official link · last checked 29 Jul 2026 Exact normalized planning authority and local planning reference in the indexed official planning record.Open official planning file · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
4 No Apartments in a Two Storey Block at 88-91 Tinnycross Park, Ballymore Eustace, County Kildary.
Floor area stated for this source: 109 m².
Source unit value with scope not stated: 4 units. It is not presented as notice-specific scale.
24 No Two Storey Dwellings at 64-87 Tinnycross Park Ballymore Eustace, County Kildare.
Floor area stated for this source: 2,681 m².
38 No Two Storey Dwellings at 26-63 Tinnycross Park, Ballymore Eustace, County Kildare.
Floor area stated for this source: 4,437 m².
8 No Two Storey Dwellings at 18-25 Tinnycross Park, Ballymore Eustace, County Kildare.
Floor area stated for this source: 878 m².
Source unit value with scope not stated: 8 houses. It is not presented as notice-specific scale.
17 No Two Storey Dwellings at 1-17 Tinnycross Park, Ballymore Eustace, County Kildare.
Floor area stated for this source: 2,096 m².