Site start

Housing site start — Donabate

Donabate, Dublin

3 commencement notices · latest start date 30 Sep 2022 · planning reference given

Planning F20A/0510 · Planning application

View full project timeline

Commencement notices
3
Latest start date
30 Sep 2022
Latest notice
24 units
Planning reference
F20A/0510
Location
Donabate, Dublin

Location

Where the site is

Area
Donabate, Dublin
County
Dublin
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Use the planning reference with the official register or the PlanningBrief council overview below.

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

Notice 1 Seven-day notice

The development shall consist of one residential building. The building is served by a single escape stair connecting ground floor to third. The building will provide 24 units consisting of one and two bedroom apartments.

Work stated for this notice 24 units Explicit phase quantity stated by the source.

Floor area stated for this source: 2,120 m².

Planning reference F20A/0510
Notice 2 Seven-day notice

The building shall consist of 4 No. single storey apartments with own door access beneath 4 No. duplexes accessed via external stepped access routes.

Work stated for this notice 8 units Explicit phase quantity stated by the source.

Floor area stated for this source: 1,149 m².

Planning reference F20A/0510
Notice 3 Commencement notice

The development will comprise:- (i) Construction of 40 No. houses, comprising of 12 No. four-bedroom, 2-storey, semi-detached houses; 24 No. three-bedroom, 2-storey, semi-detached / terrace houses; and 4 No. two-bedroom, 2-storey, terrace houses. Each dwelling will feature a private rear garden and roof mounted solar panel or photovoltaic panels; (ii) Construction of 32 No. apartment/duplex units, comprising of 15 No. two-bedroom apartments and 4 No. three-bedroom duplex units and 13 No one bedroom apartments. Each apartment/duplex unit is provided with a private balcony or terrace. The 2 No. blocks proposed are served by 225sqm of communal amenity space and roof mounted solar panel or photovoltaic panels. The proposed development includes 114 No. car parking spaces, inclusive of 76 No. on-curtilage car parking spaces serving the houses (2 No. spaces per 3 and 4 bedroom house and 1 No. space per 2 bedroom house), 32 No. car parking spaces serving the apartments/duplex units and 6 No. visitor car parking spaces, and 92 No. bicycle parking spaces (56 No. provided in 1 No. secure bicycle storage area and 36 No. provided throughout the development); (iii) Construction of a 1,800sqm public open space area, featuring a 250-sqm playground, in the north-western corner of the site; (iv) Creation of new vehicular entrance from New Road along the site's southern boundary; (v) Alterations to existing site levels through the importation of clean, uncontaminated soil and stones to the site; and (vi) All associated site, landscaping and infrastructural works, including tree planting, boundary treatments; street lighting; ESB substations; internal roadways, footpaths and shared surfaces; and foul/SuDS drainage, necessary to facilitate the development. Temporary permission (5 years) is also sought for; (i) the erection of 3 No. advertising signs (totaling 42sqm), for the purposes of marketing, on the sites eastern and southern boundaries.

Work stated for this notice 40 units Explicit phase quantity stated by the source.

Floor area stated for this source: 4,829 m².

Planning reference F20A/0510

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.