Commencement notice group
Clonshaugh Business & Technology Park — commencement notices
Dublin 17, Dublin
6 unique commencement events · latest notified commencement 05 Dec 2022 · planning basis not stated
- Unique commencement events
- 6
- Latest notified commencement
- 05 Dec 2022
- Latest notice
- 123 m²
- Planning references supplied
- None stated
- Public location
- Dublin 17, Dublin
Commencement and completion records
Planning, start and completion evidence
The certificate is linked to its commencement notice. A corresponding planning record has not yet been established from the available source evidence.
- Exact planning records
- Official record actions
- 0
- Explicit planning relationships
- Duplicate source rows consolidated
- Exact completion events
Planning-anchored public geography
Site identity and location
- Canonical public locality
- Dublin 17, Dublin
- County
- Dublin
Notice location variants
- Clonshaugh Business & Technology Park, Coolock, Dublin 17 CN0096042DC
- Coolock, Dublin 17, Dublin CN0096041DC
- Clonshaugh Business and Technology Park, Coolock, Dublin 17 CN0096041DC, CN0095338DC
- the Data Centre Facility, Clonshaugh Business & Technology Park, Coolock, Dublin 17 CN0096039DC, CN0096038DC
- Notice source points are up to 900 m apart, so no combined representative point is shown.
Source positions remain separate:
- CN0096042DC · 53.398743, -6.219016 Open point
- CN0096041DC · 53.399109, -6.216293 Open point
- CN0096039DC · 53.398202, -6.218342 Open point
- CN0096038DC · 53.398413, -6.218448 Open point
- CN0095339DC · 53.400454, -6.205742 Open point
- CN0095338DC · 53.398706, -6.217279 Open point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
No planning reference is supplied for this notice group.
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
This record remains its own commencement notice group because no shared planning-reference context is available. The grouping does not establish construction progress or completion.
Extension to an existing Substation Building at Clonshaugh Business & Technology Park, Coolock, Dublin 17.
Floor area stated for this source: 123 m².
Security Hut at Clonshaugh Business and Technology Park, Coolock, Dublin 17.
Floor area stated for this source: 123 m².
Sprinkler Pump Building at the Data Centre Facility, Clonshaugh Business & Technology Park, Coolock, Dublin 17.
Floor area stated for this source: 123 m².
New MV Building at the Data Centre Facility, Clonshaugh Business & Technology Park, Coolock, Dublin 17
Floor area stated for this source: 123 m².
Data Centre B, Clonshaugh Business and Technology Park, Coolock, Dublin 17, 2 Storey Data Centre.
Floor area stated for this source: 1,421 m².
Data Centre A, Clonshaugh Business and Technology Park, Coolock, Dublin 17, Construction of 2 Storey Data Centre at Clonshaugh Business and Technology Park, Coolock, Dublin 17.
Floor area stated for this source: 12,874 m².
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.