Site start

Housing site start — Dublin

Dublin

2 commencement notices · latest start date 02 Apr 2024 · planning reference given

Planning ABP-311671-21

Commencement notices
2
Latest start date
02 Apr 2024
Latest notice
36 units
Planning reference
ABP-311671-21
Location
Dublin

Commencement and completion records

Planning, start and completion

The certificate is linked to its commencement notice. A corresponding planning record has not yet been established from the available source evidence.

Planning applications
Links to official records
0
Links between applications
Repeat copies merged
Completion certificates

Location

Where the site is

Area
Dublin
County
Dublin
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Official source links are available below.

  • Official appeal case Appeal decision and documents Inspector's report, order, direction and meeting record for ABP-311671-21. An Coimisiún Pleanála Official link · not recently checked Exact official source shared from the planning and approval record.
    Open official appeal/SHD case · external

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

Notice 1 Commencement notice

Construction of 36 no. new apartment units and associated site works, nos. 22-57 inclusive Bentley Pines, Brighton Road, Foxrock, Co. Dublin.

Work stated for this notice 36 units Explicit phase quantity stated by the source.

Floor area stated for this source: 6,588 m².

Appeal reference ABP-311671-21
Notice 2 Commencement notice

Construction of 21 no. new dwelling houses and associated site works, nos. 1-21 inclusive Bentley Pines, Brighton Road, Foxrock, Co. Dublin.

Work stated for this notice 21 houses Explicit phase quantity stated by the source.

Floor area stated for this source: 2,730 m².

Appeal reference ABP-311671-21