Site start
Housing site start — Killimer
Killimer, Clare
4 commencement notices · latest start date 15 Apr 2026 · planning reference given
Planning ABP-319080-24
- Commencement notices
- 4
- Latest start date
- 15 Apr 2026
- Latest notice
- 38 m²
- Planning reference
- ABP-319080-24
- Location
- Killimer, Clare
Location
Where the site is
- Area
- Killimer, Clare
- County
- Clare
Addresses on the notices
- Moneypoint Power Station, Carrowdotia, Killimer, Co
- Clare
- Notice source points are up to 178.8 km apart, so no combined representative point is shown.
Source positions remain separate:
- Public notice source · 52.608550, -9.426821 Open point
- Public notice source · 52.608550, -9.426821 Open point
- Public notice source · 52.608550, -9.426821 Open point
- Public notice source · 53.581276, -7.293497 Open point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
Official source links are available below.
-
Official appeal case Appeal decision and documents Inspector's report, order, direction and meeting record for ABP-319080-24. An Coimisiún Pleanála Official link · not recently checked Exact official source shared from the planning and approval record.Open official appeal/SHD case · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
Proposed HFO Bund B Electrical Supply Container - single storey prefabricated container housing a singular transformer and associated control panels.
Floor area stated for this source: 38 m².
Proposed HFO Bund A Electrical Supply Container - Sngle storey prefabricated container housing a singular transformer and all associated control panels at Moneypoint Power Station, Carrowdotia, Killimer, Co. Clare
Floor area stated for this source: 38 m².
Construction of new LV E-House supplying power to the proposed auxiliary boiler building. The E-House will contain two power transformers. The building is a single storey construction, constructed from a steel frame and fire rated cladding.
Floor area stated for this source: 51 m².
Construction of a new boiler house (24m long x 18m wide x 11m high) to house auxiliary boilers (2 no. electric and 1 no. distillate), including an external blowdown vessel and bund, a 30m high exhaust stack and all ancillary site works.
Floor area stated for this source: 435 m².