Malahide, Co. Dublin, Dublin
4 commencement notices · latest start date 28 Sep 2021 · planning references given
Planning SHD/013/19; ABP-305991-19
- Commencement notices
- 4
- Latest start date
- 28 Sep 2021
- Latest notice
- 11,725 m²
- Planning references
- SHD/013/19 · ABP-305991-19
- Location
- Malahide, Co. Dublin, Dublin
Location
Where the site is
- Area
- Malahide, Co. Dublin, Dublin
- County
- Dublin
Addresses on the notices
- Malahide, Dublin
- Seamount Road, Seamount Abbey, Malahide, Co
- Notice source points are up to 322 m apart, so no combined representative point is shown.
Source positions remain separate:
- Public notice source · 53.443894, -6.147462 Open point
- Public notice source · 53.442666, -6.145171 Open point
- Public notice source · 53.442161, -6.149962 Open point
- Public notice source · 53.443705, -6.147874 Open point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
Official source links are available below.
-
Official appeal case Appeal decision and documents Inspector's report, order, direction and meeting record for ABP-305991-19. An Coimisiún Pleanála Official link · not recently checked Exact official source shared from the planning and approval record.Open official appeal/SHD case · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
Blocks of 76 no. apartments above shared basement with associated site works. Phase 3 of SHD/013/19
Floor area stated for this source: 11,725 m².
Source unit value with scope not stated: 76 units. It is not presented as notice-specific scale.
40 no. dwellings and the retaining wall with associated site works. Phase 2 of SHD/013/19.
Floor area stated for this source: 5,760 m².
Development of 7 no. dwellings - Phase 1 of the development under SHD/013/19 Planning Permission Grant ABP-305991-19 for development of 142 residential units (58 no. houses, 76 no. apartments, 8 no. maisonette apartments), childcare facility and associated site works at Seamount Road, Seamount Abbey, Malahide, Co. Dublin. Phase 1 Development of 7 no. dwellings involves 4 no. two storey 3 bed terraced houses type D, 2 no. two storey 4 bed semi- detached houses type A and 1 no. 2 storey 4 bed detached house type C.
Floor area stated for this source: 935 m².
Source unit value with scope not stated: 142 units. It is not presented as notice-specific scale.
Enabling works consisting of construction of Haul Road, Site Compound, Foul Drainage line, Storm Drainage line, Movement of existing mounds of subsoil on site, Earthworks for roads, Security lighting and Watermain diversion pipes. These works are in relation to the development under Planning Permission Grant ABP-305991-19 for development of 142 residential units (58 no. houses, 76 no. apartments, 8 no. maisonette apartments), childcare facility and associated site works at Seamount Road, Seamount Abbey, Malahide, Co. Dublin. Building works (142 units, childcare facility) will be a subject of a separate Commencement Notice with documentation (Long Form).