Site start
Our Lady’s Hospital — site start
Navan, Meath
2 commencement notices · latest start date 02 Feb 2026 · planning reference given
Planning 2460754 · Planning application · Council file · external
- Commencement notices
- 2
- Latest start date
- 02 Feb 2026
- Latest notice
- 138 m²
- Planning reference
- 24/60754
- Location
- Our Lady’s Hospital, Navan, Meath
Linked records
Planning, start and completion
- Planning applications
- 1
- Links to official records
- 1
- Links between applications
- 0
- Repeat copies merged
- 1
- Completion certificates
- 0
- Open exact official planning record: 24/60754 Meath County Council
Planning, commencement and completion remain separate exact-source events. Dated certificates are linked by their official notice reference and authority to the associated commencement history; notice quantities are never added into a project total.
Location
Where the site is
- Area
- Navan, Meath
- County
- Meath
Addresses on the notices
- Our Lady’s Hospital, Navan, Meath
- Navan Hospital, Navan, Meath
- Approximate commencement source point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
The exact official planning file is available below.
-
Official planning file Meath County Council planning record Application details, status and decision record for 24/60754. Official council planning portal Official link · not recently checked Exact normalized planning authority and local planning reference in the indexed official planning record.Open official planning file · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
The development will consist of a 61sq.m extension, consisting of an electrical workshop and a gas store, to the existing maintenance building. Internal Modifications to 3no. rooms and the front elevation of the maintenance building for the proposed electrical upgrade to the hospital campus. The individual areas are referred to as sites B and C in the application.
Floor area stated for this source: 138 m².
Proposed Accommodation for the new electrical substation. The works will comprise alterations to the previously approved electrical substation (PA Reference 24/60166 & 23/634) at Our Lady’s Hospital, Navan, Co. Meath. The individual area is referred to as sites A application.
Floor area stated for this source: 25 m².
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.