Site start

Building extension site start — Ballyconnell

Ballyconnell, Cavan

2 commencement notices · latest start date 08 Nov 2024 · planning reference given

Planning 21274 · Planning application · Council file · external

View full project timeline

Commencement notices
2
Latest start date
08 Nov 2024
Latest notice
544 m²
Planning reference
21274
Location
Ballyconnell, Cavan

Linked records

Planning, start and completion

Planning applications
1
Links to official records
1
Links between applications
0
Repeat copies merged
1
Completion certificates
0

Planning, commencement and completion remain separate exact-source events. Dated certificates are linked by their official notice reference and authority to the associated commencement history; notice quantities are never added into a project total.

Location

Where the site is

Area
Ballyconnell, Cavan
County
Cavan

Addresses on the notices

  • Ardue, Ballyconnell, Co
  • Arude, Ballyconnell, Co
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

The exact official planning file is available below.

  • Official planning file Cavan County Council planning record Application details, status and decision record for 21274. Official council planning portal Official link · not recently checked Exact normalized planning authority and local planning reference in the indexed official planning record.
    Open official planning file · external

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

Notice 1 Commencement notice (owner-supplied)

Construct (a) slatted shed incorporating central feed passage and cattle pens (b) machinery shed with sheep housing and handling facility (c) 2 no silage pits (d) concrete aprons and associated site works at Ardue, Ballyconnell, Co. Cavan.

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 544 m².

Planning reference 21274 Developer stated: Crust & Crumb Ireland Ltd
Notice 2 Commencement notice (owner-supplied)

Construct extension to existing slatted shed incorporating slatted section /underground tank and cattle pens, concrete aprons and associated site works at Arude, Ballyconnell, Co.Cavan. (Phase 1)

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 266 m².

Planning reference 21274 Developer stated: Crust & Crumb Ireland Ltd

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.