Site start
Newmarket Square — site start
Dublin 8, Dublin
1 commencement notice · start date 02 Sep 2021 · planning references given
Planning ABP-307067-20 & SHD0007/20
- Commencement notices
- 1
- Latest start date
- 02 Sep 2021
- Latest notice
- 413 units
- Planning references
- SHD0007/20 · ABP-307067-20
- Location
- Dublin 8, Dublin
Location
Where the site is
- Area
- Dublin 8, Dublin
- County
- Dublin
Addresses on the notices
- Newmarket Square, Dublin 8
- Approximate commencement source point
Source meaning
What the commencement source confirms
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.
Dates, scale and organisations below stay attached to the individual notice that supplied them.
Official sources
Official planning documents
Official source links are available below.
-
Official appeal case Appeal decision and documents Inspector's report, order, direction and meeting record for ABP-307067-20. An Coimisiún Pleanála Official link · not recently checked Exact official source shared from the planning and approval record.Open official appeal/SHD case · external
These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.
Chronological source evidence
Commencement notice timeline
These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.
The works provide for the construction of 13 new levels of a Residential development at Newmarket Square, Dublin 8. The works include the construction of all the building fabric above the level of the ground floor slab together with the installation of all associated building services.
Floor area stated for this source: 59,140 m².
A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.