Devoy Quarter — commencement notices

Naas, Kildare

1 unique commencement event · latest notified commencement 21 Mar 2022 · planning reference supplied

Unique commencement events
1
Latest notified commencement
21 Mar 2022
Latest notice
10,922 m²
Planning references supplied
ABP-311161-21
Public location
Naas, Kildare

Commencement and completion records

Planning, start and completion evidence

The certificate is linked to its commencement notice. A corresponding planning record has not yet been established from the available source evidence.

Exact planning records
Official record actions
0
Explicit planning relationships
Duplicate source rows consolidated
Exact completion events

Planning-anchored public geography

Site identity and location

Canonical public locality
Naas, Kildare
County
Kildare

Notice location variants

  • Devoy Quarter, Naas Road, Naas, Co CN0087293KE
Approximate commencement source point. Use the source links if the inline map is unavailable.
  • Approximate commencement source point
Approximate source location from the commencement record; not an official site boundary.

Source meaning

What the commencement source confirms

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed.

Dates, scale and organisations below stay attached to the individual notice that supplied them.

Official sources

Official planning documents

Official source links are available below.

  • Official appeal case Appeal decision and documents Inspector's report, order, direction and meeting record for ABP-311161-21. An Coimisiún Pleanála Official link · not recently checked Exact official source shared from the planning and approval record.
    Open official appeal/SHD case · external

These links are source-backed navigation. The notice-supplied planning reference remains separate from any verified canonical planning relationship.

Chronological source evidence

Commencement notice timeline

These records are grouped because they share the same planning authority and supplied planning-reference context. Each notice remains separate evidence; the grouping does not establish overall scheme scale, construction progress or completion.

CN0087293KE BCMS owner-supplied export

Alterations to previously permitted ABP-307258-20 for alteration to red line boundary, parking layouts, bin and bike stores, re- orientation of permitted creche, revisions to entrances to permitted blocks 3,4,5,7,8,9 and associated site works all at Devoy Quarter, Naas Road, Naas, Co. Kildare

Work stated for this notice Scale not stated for this notice.

Floor area stated for this source: 10,922 m².

Source unit value with scope not stated: 152 units. It is not presented as notice-specific scale.

Appeal reference ABP-311161-21 Builder stated: Randelswood Holdings Ltd Developer stated: Randelswood Holdings Ltd

A commencement notice records a declared building-control commencement date. It does not by itself confirm that every permitted work began or was completed. Future verified planning enrichment can be added to this record without changing its notice evidence.