Infrastructure · Co. Cavan

Corgarry Cabra Cormey and Mullantra, Kingscourt, Co. Cavan

Decision to grant 21 Jul 2026

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2660289 at Corgarry Cabra Cormey and Mullantra, Kingscourt, Co. Cavan: To upgrade the Kingscourt Wastewater Treatment Plant in the townland…
  • The applicant is Uisce Éireann. The agent is Emily Gallagher.
  • It was received by Cavan County Council on 27 May 2026.
  • Status: Decision to grant 21 Jul 2026.
  • The council decided on 21 Jul 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

Source: the Cavan County Council planning register, checked 11 Aug 2026. Open the council's file

More planning applications in Kingscourt · Planning applications in Co. Cavan

What and where

To upgrade the Kingscourt Wastewater Treatment Plant in the townland…

for a 10-year planning permission for works to upgrade the Kingscourt Wastewater Treatment Plant (WwTP) in the townland of Corgarry, and construction of an outfall pipeline in the public road corridor and in private lands in the townlands of Corgarry, Cabra, Cormey and Mullantra, all in the Electoral Division of Kingscourt in County Cavan. The proposed development consists of the following works: (1) Demolition of existing Inlet Works and replacement with new Inlet Works including a Dual Function Overflow Chamber, Flume, Screens, and Grit and Grease removal units; (2) Decommissioning of the existing Storm Water Tank and the Storm Water Overflow (SWO) outfall at the WwTP; (3) New Dual Function Overflow outfall pipe connection from the new WwTP Inlet Works to the single outfall to the Cabra Stream (Glyde_010); (4) 1 no. new underground Storm Water Holding Tank and associated SWO outfall pipe connection via a single outfall to the Cabra Stream (Glyde_010), adjacent to the WwTP; (5) 1 no. new underground drainage attenuation tank; (6) Outfall Pumping Station and new Primary Discharge Outfall pipe from the WwTP (ca. 3km) to the River Lagan (Glyde_020); (7) Chemical storage tanks and dosing equipment for alkalinity boosting phosphorus removal and sludge treatment; (8) 1 no. Sludge Dewatering building, 1 no. Welfare building and 1 no. of Motor Control Centre (MCC) kiosk; (9) An odour control unit consists of High-Density Polyethylene carbon filter units and associated above ground ductwork; (10) A new Electricity Supply Board substation; (11) Demolition of the existing tanks and structures not used in the future design, i.e., inlet works, primary settling tank, trickling filters, rotating biological contactor, hummus/settlement tank, storm tanks, sludge mixing tank, sludge holding tank, return pump sump, admin building, and reed beds area; (12) Extension of internal access road and provision of a turning head; (13) Demolition of the existing access bridge over the watercourse at the north boundary, and construction of a new access road and bridge; (14) Open tank process units, including below and above ground pump and drainage chambers, effluent pumping station with a surge vessel, biological reactors, clarifiers, and sludge treatment units; (15) Ancillary works: a) Access platforms; b) Provision of a back-up generator with a built-in diesel tank to be used in an emergency/power cut; c) Provision of paved/peb

Description as published by the council. Its text starts part-way through a sentence.

Location
Kingscourt, Co. Cavan Map
Planning reference
2660289

Numbers and dates

Project type
Infrastructure
Received
27 May 2026
Decision to grant
21 Jul 2026Final grant not yet recorded

Timeline

  1. Application received
  2. Decision to grant

Outlook

What happens next

The council decided on 21 Jul 2026 to grant permission. Final grant not yet recorded. No site start has been filed yet.

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2660289 on eplanning.ie: drawings, reports and the decision.Open the council's file

Reviewed build intelligence

What the documents establish

Government document review

Council decision dated 21 July 2026 with 13 conditions, explicitly not a final grant. The report is the final planning version issued on 19 May 2026 and received on 27 May. The selected records do not establish construction or later licensing compliance.

2 official documents inspected · Checked 2026-09-05 · Official file index

The proposed treatment capacity rises to 5,700 population equivalent

Proposed in application · Exact wastewater-plant upgrade proposal under application 2660289

What the evidence says
The planning report proposes increasing Kingscourt wastewater treatment design capacity from 2,400 to 5,700 population equivalent over a 25-year design horizon. This is wastewater design loading, not a housing-unit count or a measured current population.

Why it may matter — interpretation
Interpretation: establishes the scale of the process upgrade using its own engineering measure.

What is not established
Commissioned treatment performance, a final grant and additional homes served are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.11
from 2,400 p.e. to 5,700 p.e. (25-year design horizon) · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

from 2,400 p.e. to 5,700 p.e. (25-year design horizon)

The proposed process and outfall are separate packages

Proposed in application · Plant-process and primary-discharge infrastructure in the May planning design

What the evidence says
The report includes replacement inlet works, biological reactors, clarifiers, chemical dosing and sludge treatment. It also proposes an outfall pumping station and approximately three kilometres of new primary-discharge pipe to the River Lagan. Existing structures not required for the future process would be demolished.

Why it may matter — interpretation
Interpretation: distinguishes treatment equipment, decommissioning and the off-site outfall work.

What is not established
A supplier award, selected pump model, installed pipework and completed treatment plant are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.11
new Primary Discharge Outfall pipe from the WwTP (ca. 3km) · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

new Primary Discharge Outfall pipe from the WwTP (ca. 3km)

The odour-control proposal identifies HDPE carbon-filter units

Proposed in application · Odour-control package within the proposed wastewater treatment upgrade

What the evidence says
The report describes an odour-control unit comprising high-density polyethylene carbon-filter units with associated above-ground ductwork. This is a proposed equipment material and treatment approach, without a named product or supplier.

Why it may matter — interpretation
Interpretation: makes the selected treatment approach visible without inferring a manufacturer.

What is not established
Final detailed sizing, manufacturer, purchase and installed performance are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.11
High-Density Polyethylene (HDPE) carbon filter units · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

High-Density Polyethylene (HDPE) carbon filter units

The roof plan allocates 94 proposed solar panels across three buildings

Proposed in application · May planning report: three specified roofs within the wastewater plant

What the evidence says
The report allocates 24 panels to the welfare building, 60 to the sludge-dewatering building and 10 to the MCC 1 kiosk. They are landscape-oriented and flush-mounted at the respective roof pitches of 22, 15 and 11 degrees. The total is 94 proposed panels, not an installed or procured array.

Why it may matter — interpretation
Interpretation: provides an exact allocation and mounting intent for the solar work.

What is not established
Panel model, rated electrical capacity, purchase, grid approval and installation are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.19
a total of 94 No. solar panels · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

a total of 94 No. solar panels

The proposed access bridge uses precast beams and an in-situ deck

Proposed in application · Proposed access across the Cabra Stream; dimensions are design values

What the evidence says
The report places a replacement bridge roughly 11 metres east of the existing crossing. It describes two concrete abutments, precast beams and an in-situ concrete deck, with a nine-metre clear span and 1.7 metres clearance above normal stream level. The existing crossing would be removed.

Why it may matter — interpretation
Interpretation: identifies the separate bridge structure needed for construction and maintenance access.

What is not established
Final bridge design approval, precast supplier, installed dimensions and completed works are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.15
with precast bridge beams placed on the abutments · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

with precast bridge beams placed on the abutments

The report sets out a sequence for access, process and demolition work

Proposed in application · Proposed construction sequence within one treatment-plant upgrade; not observed progress

What the evidence says
The proposed initial phase relocates services and builds the substation, replacement access and pumped outfall. New southern process units and MCC 1 follow, then northern sludge and chemical facilities. The western demolition, new storm tank and administration building are described as the final sequence.

Why it may matter — interpretation
Interpretation: connects enabling, process and demolition packages without presenting the plan as a live construction programme.

What is not established
Actual commencement dates, completed stages, appointments and a contractual programme are not established.

Inspect the evidence

Kingscourt wastewater upgrade: planning report · p.15
Initially, re-routing of existing services will take place · Issued 2026-05-19 · Final Version for Planning; control table distinguishes earlier review drafts; received 2026-05-27 · Checked 2026-09-05

Initially, re-routing of existing services will take place

The council decision requires an EPA licence-review application before works

Council condition; later compliance not inspected · Condition 2 in the council decision of 21 July 2026

What the evidence says
Condition 2 requires an application for review of the wastewater discharge licence within six months of the final grant and before development starts, unless the EPA agrees otherwise in writing. The decision notice itself is explicitly not a grant of permission.

Why it may matter — interpretation
Interpretation: records the document’s stated dependency before construction; it is not evidence that the licence review was completed.

What is not established
A later final grant, licence-review submission, EPA agreement and actual start are not established.

Inspect the evidence

Kingscourt wastewater upgrade: council decision · p.2
THIS NOTICE IS NOT A GRANT OF PERMISSION · Issued 2026-07-21 · Decision with 13 conditions; not a final grant · Checked 2026-09-05

THIS NOTICE IS NOT A GRANT OF PERMISSION

Kingscourt wastewater upgrade: council decision · p.3
within six months of the date of the final grant of permission · Issued 2026-07-21 · Decision with 13 conditions; not a final grant · Checked 2026-09-05

within six months of the date of the final grant of permission
Remaining document questions
  • Which later official decision, approved detail or revision changes these source-specific findings?
  • Has a phase-specific official record established the selected equipment or installed specification?

Selected pages of 2 government-published PDFs were visually inspected. The exact council index lists 64 document rows. Only cited pages of 2 selected government-published PDFs establish these findings; the remaining catalogue has not been reviewed. Proposals do not establish procurement or installed work.

How we know this

From the Cavan County Council planning register, checked 11 Aug 2026. We link to the council's own file so you can check the official record before you act. Facts from the planning documents were read from the documents in that file.

Explore the area

More planning activity near Kingscourt

Get alerts for KingscourtFree. We email you when new applications appear.

Free email alerts

Get new Kingscourt projects by email

New applications, decisions and site starts in Kingscourt, Co. Cavan. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options