Back to leads
Est. value
€3m–10m
Units
13
Floor area
878 m²
Commenced
31 Dec 2024
Commencement
13 dwellings, Cootehill, Cavan - Planning Application PT8CN86
Cavan / Cootehill / Cootehill, Cavan
Source-linked planning record
13 dwellings, Cootehill, Cavan - Planning Application PT8CN86
Cavan / Cootehill / Cootehill, Cavan- PB ref
- PB-1756158012
- Plan ref
- PT8CN86
- Authority
- Cavan County Council
- Stage / date
- Commencement / 31 Dec 2024
- Est. value band
- €3m–10m
- Units / floor
- 13 / 878 m²
- Project class
- Small multi-unit
- Promoter
- Cavan Co Council
- Architect / agent
- Sandar Ltd T/a Sandar Construction
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Cavan County Council
- Application reference
- PT8CN86
- Applicant
- Cavan Co Council
- Agent
- Sandar Ltd T/a Sandar Construction
- Decision stage
- Commencement
- Commenced
- 31 Dec 2024
- Units
- 13
- Floor area
- 878 m²
- Builder / developer
- Sandar Ltd T/a Sandar Construction
Official description
Verbatim source text
Erection of mixed residential development of 13 no. dwellings (9 no. 1 bedroom maisonette, 1 no. 2 bedroom maisonette and 3 no. 3 bedroom houses), access via existing service road, connect to public foul and storm water sewers, public watermains & all ancillary works.
Verify against official sourceExplore the area
More Cavan planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- Cavan Co Council
- Planning agent
- Sandar Ltd T/a Sandar Construction
- Builder / developer
- Sandar Ltd T/a Sandar Construction
Lifecycle timeline
Application to site progress
-
Applied
31 Dec 2024 PT8CN86 -
Decision
Commencement notice filed 31 Dec 2024 -
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Commenced
No commencement indexed No reliable public commencement record is indexed against this permission. -
Completed
Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Likely trades & supplier leads