Planning record · Co. Clare
29 Rosanore, Lifford, Ennis, Co. Clare
Granted 2 Jun 2017 (final grant issued 3 Jul 2017)
We no longer update this application, so we can't email you about it. Get new planning applications in Ennis by email
Key facts
- Planning application 17266 at 29 Rosanore, Lifford, Ennis, Co. Clare: Single storey extension to the rear of existing crèche building.
- It was received by Clare County Council on 13 Apr 2017.
- Status: Granted 2 Jun 2017 (final grant issued 3 Jul 2017).
Source: the Clare County Council planning register, as last seen on 12 Jun 2026. Open the council's file
More planning applications in Ennis · Planning applications in Co. Clare
Council register
The council's register shows: Granted on 2 Jun 2017.
Search the Clare planning register
Application details as we last saw them in the national register on 12 Jun 2026.
What and where
Single storey extension to the rear of existing crèche building
to construct a single storey extension to the rear of existing crèche building, with all associated site works
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Ennis, Co. Clare Map
- Council
- Clare County Council
- Planning reference
- 17266
Numbers and dates
- Project type
- Planning record
- Received
- 13 Apr 2017
- Decision to grant
- 2 Jun 2017
- Final grant
- 3 Jul 2017
- Site start notified
- 28 Aug 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 17266 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Clare County Council planning register, as last seen on 12 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 28 Aug 2019Notice filed · Construction of single storey extension to rear of existing creche building with all...View the site start
- Completion certificate recordedRecorded in Aug 2019 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.