2 dwellings, Bunratty, Clare - Planning Application 2460004
Clare / Bunratty / Bunratty, Clare
Source-linked planning record
2 dwellings, Bunratty, Clare - Planning Application 2460004
Clare / Bunratty / Bunratty, Clare- PB ref
- PB-21061
- Plan ref
- 2460004
- Authority
- Clare County Council
- Stage / date
- Commencement / 6 Aug 2025
- Est. value band
- €500k–1m
- Units / floor
- 2 / 568 m² (per planning documents)
- Project class
- Small residential
- Promoter
- Conradh Construction Ltd
- Architect / agent
- Conradh Construction Ltd
Source: http://www.eplanning.ie/ClareCC/AppFileRefDetails/2460004/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Clare County Council
- Application reference
- 2460004
- Applicant
- Conradh Construction Ltd
- Agent
- Conradh Construction Ltd
- Decision stage
- Commencement
- Commenced
- 6 Aug 2025
- Units
- 2
- Floor area
- 568 m² (per planning documents)
- Builder / developer
- Conradh Construction Ltd
Document insights
Extracted from official planning documents
- Unit mix
- 2 4 Bed
- Floor area (per planning documents)
- 568 m²
- Site area
- 0.129 ha
- Applicant / promoter
- Mulkear Investments Ltd
- Scope
- Construction of 2 two-storey detached dwellings with garages, accesses, parking, boundary treatment, and site services.
Facts only, extracted from official planning documents. Drawings and document packs are not republished.
source: Application Form - Part A, Clare County Council planning file
Official description
Verbatim source text
to construct 2 no. two-storey detached dwellings and 2 no. ancillary single storey garages to the rear along with 2 no. individual vehicular and pedestrian accesses, parking, boundary treatment and connections to adjacent services/utilities inclusive of all associated site works
Verify against official sourceMore Clare planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- Conradh Construction Ltd
- Planning agent
- Conradh Construction Ltd
- Builder / developer
- Conradh Construction Ltd
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Commenced
6 Aug 2025 Work started · 2no. two storey detached dweelings and 2no. ancilary single storey garage/storage to the... -
Completed
Completion not recorded No privacy-cleared exact completion certificate is linked to this permission. Absence is not evidence that the project is incomplete.
Likely trades & supplier leads